- QA - just needs to finish last 4 P1 Locale tests
- Overall- We plan to hold 1.0.8 for simultaneous release with 1.5.0.2 <<== Decision
1.7.13
- Build: We have builds done for 10.2, 10.4. Should be cleaned up and ready to go by 3pm today
- Problem was the tool chain
- See email with all the builds/toolchain color coding. (Very painful ;) )
- Interaction between mac version, toolchain, xcode (dev tool set form Apple AKA "Developer Tool kit")
- Need to build on 10.2; we were building on 10.3
- QA - Test all Mac versions
- Launch on all three MacOSs
1.5.0.2
- Dave wants JA build for Ja team testing
- To test core fixes for JA
- Win only, JA-jp
- Mac Universal Binaries (UB)
- Smoke test on MacPPC - Done
- When UB is done, we will do some minor retesting of PPC.
- Dave is posting an outline of what PPV and Intel Mac testing should be done. This will be in the test plan?
- Verifications
- At this point 97 fixes verified - 10 more TBD by Ja
- Goal is 104 fixes verified
- Some Critical security bugs still need to be tested
- Less than 11
- Some of these can only be verified by code inspection. See the "no verification needed" flag - "nvn-dl" in the status white board.
- Others will be verified by by Bob's Security Test Library tests
- At this point 97 fixes verified - 10 more TBD by Ja
- Testing remaining before "Go" for tagging/signing and setting date for Community Test day:
- Ext test - top 10/Recommended/Ext winners
- Run Security Test Library on one plaform - Dave to check with Bob to see if this was done
- Plan to set date for Community Test Day tomorrow.
- TB testing?
- Smoke on all platforms
- BFT on Win
- Marcia will work with Scott to plan TB testing
- What % of bugs to verif for TB?
- What about UB for TB?
- Resolving UB issues
- Why core bugs need to be fixed?
- How is Camino relelasing UB
- Why no official build for UB if released for Camino
- Get Josh in Release Team tomorrow - Marcia