Start of project
- Project sponsor: Ben Galbraith and Dion Almaer
- Main IT contact
- Main WebDev contact: Laura Thomson
- Main QA contact
- Main Security contact
- Final application owner/maintainer: Developer Tools
- Outline the following:
- Overall goal of the project
- Overall project plan at https://wiki.mozilla.org/Labs/OpenWebHomePage
- Current phase at https://wiki.mozilla.org/Labs/OpenWebHomePage/ToolsDirectory
- Any pre-requisites needed (technology, server capacity, staffing, monitoring, response time, etc): stock PHP/MySQL
- Initial timeline: deliver prototype by Thursday June 25. Site to launch by end Q2.
- External dependencies: Developer Tools building front end
- Dev environment specs: as per above, stock
- Does this project use any plugins or proprietary technology? No
- Overall goal of the project
Staging Signoff
In order to get an app into staging, the following should be completed:
- Code committed to Mozilla source control and tagged - committed
- Initial architecture review by IT and WebDev - waiting on lorchard for review
- Plugin/tech review by Evangelism - no special/new tech
- Security review must be in-process
- Site must be password protected
- Review timeline to go live
- Review any production requirements so IT can order any new hardware needed
Production Signoff/Launch
- Final WebDev signoff
- Final IT signoff
- Final QA signoff
- Final Security signoff
- Operations documents filled for support & any training complete
- Monitors in place