Agenda
- FFOS
- Team meeting ideas
- Goals - next steps
Dietrich
Erin
Lawrence
Martin
Michael
Marco
This Week
- Team currently in California participating in Project Work Week.
- On Monday, Asa reviewed updated Feature Stories with development team.
- On Tuesday, estimates were completed for all P1 Feature Stories.
- On Wednesday:
- functionality testing will commence on all previously completed stories to determine if they are done.
- develop inventory of outstanding visual assets required for Feature Stories.
- re-format Metro on Bugzilla to accommodate sprint, component, story point values and updated Feature Story format.
- development team to pull Feature Stories they can commit to for the upcoming iteration.
- On Thursday:
- work on draft Forecast Release Schedule.
Sheila
- Goals
- Prep for Damon's offsite in Feb
- FHR
- Landed in Nightly, working on uplift for Aurora