Status Report: Week ending November 05th, 2010
Issues
Issue | Resolution | |
Friday: Holiday | Festival day: Diwali | |
|
|
This Week's Tasks
Test Execution
Weekly Goal | Work Completed |
Monday: -Task#2:Add-ons download testing |
Results: Hours Spent: 8 |
Tuesday:
|
Results: Issues Noticed:unreviewed add-ons download fails Hours Spent: 8 |
Wednesday:
|
Results: Hours Spent: 8 |
Thursday: |
Results: Hours Spent:8 |
Friday: |
Results: Hours Spent:NONE |
Saturday: |
Results: Hours Spent:8 |
|
|
Next Week's Tasks
- P1: Testrun Execution
- P1: Adhoc testing of new features
- P2:Test Development
- Continue creating testcases for Input Feedback pages.