Status Report: Week ending November 12th, 2010
Issues
Issue | Resolution |
|
|
This Week's Tasks
Test Execution
Weekly Goal | Work Completed |
Monday: -Task#2:Test run for AMO Search |
Results: Task#2:Updated litmus with test results Hours Spent: 8 |
Tuesday: |
Results: Hours Spent: 8 |
Wednesday: |
Results: Hours Spent: 8 |
Thursday: |
Results: Task#2:Update 12 test cases in test run for Search Hours Spent:8 |
Friday: |
Results: Task#2:Updated 15 test cases
|
|
|
Next Week's Tasks
- P1: Testrun Execution
- P1: Adhoc testing of new features
- P2:Test Development
- Continue creating testcases for Input Feedback pages.