(Created page with "=Milestone planning - May 26th -> July 7th= velocity =~ 30 We took the result of previous planning; then we estimated some of the sto...")
 
Line 6: Line 6:


== Results of the planning ==
== Results of the planning ==
===Story: Split panels in separate documents===
Inbox is nearly ready, Conversation still has some work needed. See [[#Story:_Split_panels_in_separate_documents|discussion below]].
Estimate: ~4.3 [julien 5][oleg 3][steve 5]
===Story: Define all services for Inbox panel===
See [[#Inbox|discussion below]]. This is including the mozAPI wrappers.
Estimate: ~15
===Story: IndexedDB in Gaia===
Estimate: ~10