= Objective =
Separate concerns for Integration vs. Acceptance End-to-end tests so that test processes and automation harnesses can optimize for their specific purposes and minimize risk and dependency.
= Challenges Addressed =
* Development and QA have different approaches and needs from UI testing
* Team has been blocked too much by cross-team dependencies
* The product is too unstable for acceptance end-to-end testing during development phases* Acceptance End-to-end coverage is insufficient to guarantee a quality build
= The Problem =
But not all automation is the same just because it targets the UI, just as not all testing is the same just because it targets the SUT.
In particular, integration automation run before landing a commit is subject to a series of restrictions meant to ensure that the test results are returned quickly and in an unambiguous fashion. Those restrictions reduce the usefulness of the automation for use in acceptance end-to-end testing, which must often accept a higher level of fragility and longer runtime to be more comprehensive.
When viewed through the lens of the other purpose, each type of automation is inferior:
Commit integration automation is incomplete and shallow, trading expedience for coverage, and is generally written from a developer's perspective to ensure the behavior of what they did write--which might not actually meet the requirements of what they should have written. As the tests tend to be written against a particular section or application of the SUT, broad interactions may go uncovered. Large portions of the SUT may go untested because they rely on unreliable external conditions. As such, these tests frequently fall short of the needs of acceptanceend-to-end.
Conversely, acceptance end-to-end automation is too slow, device-bound, and sometimes has spurious failures due to non-determinism inherent in the SUT and its externals. As the user scenarios it tests often bridge multiple parts of the system, it's more fragile with poor isolation. The need to rely on user-like behavior and check after every step slows the tests down. The wider scope means it often can't be written adequately until entire subsystems are in place. So these tests are often wholly unsuitable for the incremental growth, quick land-or-not decisions, and debugging assistance that a good continuous integration suite provides.
However, these are weaknesses in perception. When used for their own specific purposes, each type of automation provides great value. Further, the compromises each makes are compensated for by the other.
** Runs on B2G Desktop currently, will run on device as well soon
* Gaia AcceptanceEnd-to-end
** Can have longer-running tests and have reasonable amounts of fragility due to non-determinism
** Results can be occasionally ambiguous as a trade-off for higher coverage
* Gaia Integration tests run faster and are generally more isolated.
* Gaia Acceptance End-to-end tests have more coverage due to less rules.
* Gaia Integration tests can never fail unless there's a defective code change. They must be unambiguous.
* Gaia Acceptance End-to-end tests can still fail due to system non-determinism if they are reliable enough to be a net gain.
* Gaia Integration tests are maintained by functional teams to give themselves confidence in code changes.
* Gaia Acceptance End-to-end tests are maintained by QA to replace or extend manual acceptance end-to-end testing.
* Gaia Integration tests frequently test fragments of UI behavior and may be based on mocks or other low-level objects.
* Gaia Acceptance End-to-end tests are written as complete user-like scenarios, and operate and verify as the user would.
* It is more important that Gaia Integration tests be solid than complete. Any incremental gain is valuable.
* It is more important that Gaia Acceptance End-to-end tests be complete than solid. All acceptance end-to-end criteria must be tested to accept a build.
== Ownership and Overlap ==
Ownership is separated because these differences can lead to variations in needs for breadth and depth of testing.
Tests can and should overlap between Gaia Integration and Gaia AcceptanceEnd-to-end. It is unacceptable process complication for QA to expect developers to always consult their needs and vice versa for every change. If the test flows are shared, it's all too easy for one group to inadvertently make a change that damages the purpose of the other. For acceptanceend-to-end, in particular, this is too risky, as proper acceptance end-to-end depends on maintaining a particular scope and depth.
Avoiding these communication issues and this risk requires separate tests, even to the point where there might be tests whose flow is entirely duplicated between the two suites.
Unlike other aspects of our strategy, this is a perspective shift and articulates a dual path towards the rest of our plans:
QA has defined and will own and expand Gaia Acceptance End-to-end as an aid to its build acceptance end-to-end mandate, and functional teams will continue to own and expand Gaia Integration as an aid to stabilization and their own processes. QA will help whenever resources are available.
= Risks =
None.