Continuous Integration: Difference between revisions

Jump to navigation Jump to search
Line 39: Line 39:
|-
|-
| Convert integration tests from GIP to GIJ
| Convert integration tests from GIP to GIJ
| 12/31/15
| 03/25/16
! style="background:#FF2800;" | LATE
! style="background:#FFFF00;" | CHALLENGED
| All but 10 have been converted. This deliverable is late because intermittents were prioritized above this effort.
| Due date revised to end of Sprint 10. All but 10 have been converted. This deliverable is challenged because intermittents are a competing priority.
|-
|-
| Intermittently failing tests fixed
| Intermittently failing tests fixed
| 01/31/15
| 02/26/16
! style="background:#FF2800;" | AT RISK
! style="background:#00EC00;" | ON TARGET
| Fixed parts of Marionette that were causing issues. Disabled all the tests were failing intermittently. Module owners need to ensured they're fixed before re-enabling them. Will need more time than originally estimated so most likely won't meet due date.
| Due date revised to end of Sprint 8. Fixed parts of Marionette that were causing issues. Disabled all the tests were failing intermittently. Module owners need to ensured they're fixed before re-enabling them. Need support to prioritize this work with the engineers.
|-
|-
| Tests that work on mulet work on device
| Tests that work on mulet work on device
| 01/31/15
| 02/26/16
! style="background:#FFFF00;" | CHALLENGED
! style="background:#FFFF00;" | CHALLENGED
| It's being reported that some of the flagged tests actually work on device.  Need to reassess all.
| It's being reported that some of the flagged tests actually work on device.  Need to reassess all. This deliverable isn't being given much attention.
|-
|-
| Test Matrix created that defines platform(s) the tests are going to run on
| Test Matrix created that defines platform(s) the tests are going to run on
| 12/31/15
| 02/26/16
! style="background:#FF2800;" | LATE
! style="background:#00EC00;" | ON TARGET
| Draft of matrix completed but there are still some tests that need to be evaluated for appropriate testing environment. Won't get this done until January.
| Due date pushed out to one that is more realistic. Draft of matrix completed but there are still some tests that need to be evaluated for appropriate testing environment. Meeting with eng. mgmt. scheduled for Jan. 27th to review test matrix.
|-
|-
| Automation of tests according to Test Matrix
| Automation of tests according to Test Matrix