Connected Devices/Projects/Vaani: Difference between revisions

Jump to navigation Jump to search
(update website link2)
Line 97: Line 97:
|-
|-
| Berlin Troubleshoots Hardware and Sends to End Users
| Berlin Troubleshoots Hardware and Sends to End Users
|7/25/16 - 8/10/16
|7/25/16 - 8/22/16
! style="background:#00EC00;" | On Target
! style="background:#00EC00;" | On Target
|-
|-
| ***User testing of prototype
| ***User testing of prototype
|8/15/16- 8/25/16
|8/29/16- 9/12/16
! style="background:#00EC00;" | On Target
! style="background:#00EC00;" | On Target
|-
|-
| Surveys for User Testing Complete + Analyzed
| Surveys for User Testing Complete + Analyzed
|7/29/16
|9/19/16
! style="background:#00EC00;" | On Target
! style="background:#00EC00;" | On Target
|-
|-
| User Testing of the Prototype Complete
| User Testing of the Prototype Complete
|9/2/16
|9/19/16
! style="background:#00EC00;" | On Target
! style="background:#00EC00;" | On Target
|-
|-