Firefox/Activity Stream/Mobile Sprint Planning: Difference between revisions

Jump to navigation Jump to search
Line 2: Line 2:




== Current - Sprint 1.6 - Oct 03 - 16, 2016 ==
== Sprint 1.7 - Oct 17 - 30, 2016 ==
 
=== Goals and Outcomes ===
=== Goals and Outcomes ===
* continue push/tabs work
* Continued work on Highlights
* continue home panel work
* Handling of website metadata
* start work on iOS telemetry (based on tiles pipeline)
* Focus 2.0
 
==== Non-code outcomes ====
==== Non-code outcomes ====
* Start feeding historical performance numbers into capacity calculation sheet
* Continue managing bug assignments to reasonable/realistic capacity
* Get into the habit of NOT stockpiling bugs. Assigned to 1 or 2 only at any given time.
* Aim to have final user stories in hand, and breakdowns well underway
* Establish baseline velocity upon completion of this sprint
* Existing bugs to be sorted into themes/buckets based on high-level plans for user stories


=== Remaining Work to Complete for this Sprint ===