| User Study to validate the future experience/UX
| User Study to validate the future experience/UX
| 11/30/2016
| 11/30/2016
! style="background:#00EC00;" | On target
! style="background:#00B2FF;" | Done
| It starts on Nov 30th and finishes on Dec 2nd
| It starts on Nov 30th and finishes on Dec 2nd
|-
|-
Line 124: Line 124:
| London Pilot
| London Pilot
| 11/30/2016
| 11/30/2016
! style="background:#00EC00;" | On target
! style="background:#C1C6CA;" | Cancelled
|  
| We would not able to offer an enough compelling experience and attractive MVP client so we decided that it would be better to wait and run a user validation test with some users using a mock up. That would give us better incomes. 
|-
|-
| Hawaii working week
| Hawaii working week
| 12/21/2016
| 12/21/2016
! style="background:#00EC00;" | On target
! style="background:#00B2FF;" | Done
|  
|  
|-
|-
| Gate 1 meeting with PIB
| Gate 1 meeting with PIB
| 12/21/2016
| 01/13/2017
! style="background:#00EC00;" | Scheduled
! style="background:#00EC00;" | Scheduled
|  
| It was moved from Dec 21st to Jan 13th
|}
|}