Below is a weekly engineering development update.
Below is a weekly engineering development update.
<p> </p>
<p> </p>
==== July 24 Update ====
==== July 31 Update ====
<p> </p>
<p> </p>
* The goal of Milestone 3 to support user testing requires an expansion of the project's scope resulting in extended development effort.
* Status: '''Green''' - In Development.
* The MVP delivery date for Q1/2019 is not impacted.
* Team is [https://mzl.la/2GoDoCJ currently working on Iteration #9] which runs from July 23 - August 3.
* The scope expansion has changed the project’s metrics as follows:
* A cumulative completion of 47 bugs is required by the conclusion of Iteration #9 to remain on schedule.
** '''Backlog Size''':  From 58 total bugs to 70 total bugs.
* Team has, to date, a cumulative completion of 54 bugs for Iteration #9.
** '''Remaining Work''':  From 10 bugs to 22 bugs.
* Team has [https://mzl.la/2HyVqTB completed 87%] of the entire [https://mzl.la/2pe4jLM Milestone 1 - 3 Backlog].
** '''Percentage Complete''': From 90% to 80%.
* The forecast completion of the entire Milestone 1 - 3 Backlog is on September 28.
** '''Forecast Completion Date''':  From August 17 to September 28.
* View [https://docs.google.com/spreadsheets/d/19ZsqjD_H4fOjg7iPKBsMQ_toM1ywAvvd5hqvI0p1QGI/edit?usp=sharing Project Tracking Dashboard] for current schedule progress and backlog.
* View [https://docs.google.com/spreadsheets/d/19ZsqjD_H4fOjg7iPKBsMQ_toM1ywAvvd5hqvI0p1QGI/edit?usp=sharing Project Tracking Dashboard] for current schedule progress and backlog.
[[File:WPD CurrentUpdateNow.png|frame|center|Updated Weekly. Current Update - Tuesday, July 24.]]
[[File:WPD CurrentUpdateNow.png|frame|center|Updated Weekly. Current Update - Tuesday, July 31.]]
<p> </p>
<p> </p>


Confirmed users
4,174

edits

Navigation menu