edits
| Line 13: | Line 13: | ||
Below is a weekly engineering development update. | Below is a weekly engineering development update. | ||
<p> </p> | <p> </p> | ||
==== August | ==== August 14 Update ==== | ||
<p> </p> | <p> </p> | ||
* Status: '''Green''' - In Development. | * Status: '''Green''' - In Development. | ||
* Team is [https://mzl.la/2GoDoCJ currently working on Iteration #10] which runs from August 6 - August 17. | * Team is [https://mzl.la/2GoDoCJ currently working on Iteration #10] which runs from August 6 - August 17. | ||
* A cumulative completion of 54 bugs is required by the conclusion of Iteration #10 to remain on schedule. | * A cumulative completion of 54 bugs is required by the conclusion of Iteration #10 to remain on schedule. | ||
* Team has, to date, a cumulative completion of | * Team has, to date, a cumulative completion of 64 bugs for Iteration #10. | ||
* Team has [https://mzl.la/2HyVqTB completed | * Team has [https://mzl.la/2HyVqTB completed 95%] of the entire [https://mzl.la/2pe4jLM Milestone 1 - 3 Backlog]. | ||
* The forecast completion of the entire Milestone 1 - 3 Backlog is on September 28. | * The forecast completion of the entire Milestone 1 - 3 Backlog is on September 28. | ||
* View [https://docs.google.com/spreadsheets/d/19ZsqjD_H4fOjg7iPKBsMQ_toM1ywAvvd5hqvI0p1QGI/edit?usp=sharing Project Tracking Dashboard] for current schedule progress and backlog. | * View [https://docs.google.com/spreadsheets/d/19ZsqjD_H4fOjg7iPKBsMQ_toM1ywAvvd5hqvI0p1QGI/edit?usp=sharing Project Tracking Dashboard] for current schedule progress and backlog. | ||
[[File:WPD CurrentUpdateNow.png|frame|center|Updated Weekly. Current Update - Tuesday, August | [[File:WPD CurrentUpdateNow.png|frame|center|Updated Weekly. Current Update - Tuesday, August 14.]] | ||