August 21 Update
Below is a weekly engineering development update.
<p> </p>
==== August 21 28 Update ====<p> </p>'''Note:''' Team is currently ahead of schedule and has added a further 13 bugs to the project's MVP scope with the time remaining.
<p> </p>
* Status: '''Green''' - In Development.
* Team is [https://mzl.la/2GoDoCJ currently working on Iteration #11] which runs from August 20 - August 31.
* A cumulative completion of 70 bugs is required by the conclusion of Iteration #11 to remain on schedule.
* Team has, to date, a cumulative completion of 67 70 bugs for Iteration #11.* Team has [https://mzl.la/2HyVqTB completed 8790%] of the entire [https://mzl.la/2pe4jLM Milestone 1 - 3 Backlog].
* The forecast completion of the entire Milestone 1 - 3 Backlog is on September 28.
* View [https://docs.google.com/spreadsheets/d/19ZsqjD_H4fOjg7iPKBsMQ_toM1ywAvvd5hqvI0p1QGI/edit?usp=sharing Project Tracking Dashboard] for current schedule progress and backlog.
[[File:WPD CurrentUpdateNow.png|frame|center|Updated Weekly. Current Update - Tuesday, August 2128.]]