Line 431: Line 431:


==The following needs to be performed at the End of Early Beta==
==The following needs to be performed at the End of Early Beta==
Please Note: This is performed on the Friday at the midway point of the beta cycle, see the Releases Scheduling google calendar. This is typically after beta 6 has been released. This should be done in before pushing any other uplifts to beta after beta 6.
Please Note: This is performed on the Friday at the midway point of the beta cycle. This is typically after beta 5 has been released. This should be done before pushing any other uplifts to beta after beta 5.
# Go to [https://treeherder.mozilla.org/ Treeherder].
# Submit a Early -> late beta merge automation with Dry Run disabled in Ship-it
# Select the beta repo.
# Start the Early -> late beta merge automation
# On the latest commit push, click on the down arrow at the top right corner. Do not trigger on a tag.
# Select “Custom push action…”
# Choose ''merge-automation'' from the dropdown.
# Insert the following payload and click trigger.
<pre>force-dry-run: false
behavior: early-to-late-beta
</pre>


After the job runs, verify that the commit was pushed to the mozilla-beta repo, see [https://hg.mozilla.org/releases/mozilla-beta/rev/29e6215562511ffef7bfa73bed97093ec3d8cdd4 example].