==The following tasks need to be performed 24 hours after go-live==
==The following tasks need to be performed 24 hours after go-live==
# Review release crash rates and incoming bugs for new blockers.
# Review release crash rates and incoming bugs for new blockers.
#* Only change Desktop update rate to 0% in [https://balrog.services.mozilla.com/rules?product=Firefox&channel=release Balrog]if something is critical, otherwise leave the rate at 25% for another day,.
#* Only change Desktop update rate to 0% in [https://balrog.services.mozilla.com/rules?product=Firefox&channel=release Balrog]if something is critical, otherwise maintain the rate at 25% for another 24 hours.


==The following tasks need to be performed 48 hours after go-live==
==The following tasks need to be performed 48 hours after go-live==