=== The Revamp === | === The Revamp === | ||
Items for consideration (time estimates to come) that should be completed by late February | Items for consideration (time estimates to come) that should be completed by late February | ||
'''Format: '''['''due date] '''task''' ('''comment''') | |||
*The sites core functionality | |||
*The content overhaul and creation | *[22/11/10] The sites core functionality (ie. the bare minimum)<br> | ||
*Theme tweaks | *[29/11/10] The domain name structure (recommended: [[Websites/Taskforce/Proposals/Domain_Name_Strategy|following Mozilla]] on this one)<br> | ||
* | *[13/12/10] The content overhaul and creation (already started) | ||
* | *[03/01/11] Theme tweaks (not redesign, just minor tweaks) | ||
* | *[10/01/11] Site downtime (a maintainance page should also be created for this task) | ||
*Face-to-face meetup | *[24/01/11] Impliment changes (all of them, not just some) | ||
*[31/01/11] Relaunch site! (Yay!) | |||
*[02/11] Face-to-face meetup to work out long term plan (Double yay!) | |||
The plan for completing these should follow loosely with the unix philosophy of doing one thing and doing it well. So we should do one task, do it well, then move to the next while taking the results of the previous into account. | |||