m (→Project Status) |
m (→Project Status) |
||
| Line 23: | Line 23: | ||
*** working on a page that tracks each weekly train and each bugs progression up the channel ladder. data has been collected, just need to put it in a document. | *** working on a page that tracks each weekly train and each bugs progression up the channel ladder. data has been collected, just need to put it in a document. | ||
*** starting work on account setup test case with Mozill. | *** starting work on account setup test case with Mozill. | ||
** Server (James) | ** Server (James) | ||
*** Proof of concept Sync server installations on CentOS, EL6, Ubuntu, and Fedora are complete. | *** Proof of concept Sync server installations on CentOS, EL6, Ubuntu, and Fedora are complete. | ||
| Line 29: | Line 28: | ||
*** OPs is actively reconfiguring the Stage and Load Test environments to make them more useful to both Dev and QA for weekly trains and other off-cycle testing. | *** OPs is actively reconfiguring the Stage and Load Test environments to make them more useful to both Dev and QA for weekly trains and other off-cycle testing. | ||
*** Weekly train for Account-Portal changes has been delayed one week due to the above work. | *** Weekly train for Account-Portal changes has been delayed one week due to the above work. | ||
** Load Testing (Owen) | ** Load Testing (Owen) | ||
*** Owen is out at Automation QA Team WorkWeek in England. | *** Owen is out at Automation QA Team WorkWeek in England. | ||