| == Schedule ==
| |
|
| |
|
| {| border="1" cellpadding="2" summary="schedule table"
| |
| |-
| |
| ! Milestone !! Item !! Deps !! Time !! Who !! Completed
| |
| |-
| |
| | M1 || Initial Setup || || || ||
| |
| |-
| |
| | 1a || Choose validation Lab, approve costs, and sign NDA || all || || all || [http://www.atlanlabs.com/ Atlan]
| |
| |-
| |
| | 1d || Define Algorithms, Key Sizes and modes || || || ||
| |
| |-
| |
| | M2 || Complete NSS 3.12 FIPS dependant bugs || || || ||
| |
| |-
| |
| | M3 || Update documentation (numbers in parentheses refer to sections in FIPS documentation) || || || ||
| |
| |-
| |
| | 3a. || (1.0) Security policy, new algorithms || 1d || 2 wks || all ||
| |
| |-
| |
| | 3b. || Generate annotated source tree (LXR -> HTML) || M2 || || ||
| |
| |-
| |
| | 3c. || (2.0) Finite State Machine || 3b || 3 wks || ||
| |
| |-
| |
| | 3d. || (3.0/4.0) Cryptographic Module Definition || 3b || 2 wks || ||
| |
| |-
| |
| | 3e. || (6.0) Software Security (rules-to-code map) || 3b || 2 wks || ||
| |
| |-
| |
| | 3f. || (8.0) Key Management Generate 20K random #'s || || 1 day || ||
| |
| |-
| |
| | 3g. || (9.0) Cryptographic Algs || 3a || 3 days || ||
| |
| |-
| |
| | 3h. || (10.0) Operational Test Plan || || 1 day || ||
| |
| |-
| |
| | 3i. || Document architectural changes between 3.2 and 3.11 || || 5 days || ||
| |
| |-
| |
| | M4 || Send docs to testing lab || || || ||
| |
| |-
| |
| | 4a. || Security Policy || || all || ||
| |
| |-
| |
| | 4b. || Finite State Machine || 3c || || ||
| |
| |-
| |
| | 4c. || Module Def. / rules-to-code || 3d,3e || || ||
| |
| |-
| |
| | M5 || Operational validation || || || ||
| |
| |-
| |
| | 5a. || Algorithm testing || || 1 month || ||
| |
| |-
| |
| | 5b. || Operational testing || 3h || 1 week || ||
| |
| |-
| |
| | 5c || set up machines for Lab to run operational tests on, provide Lab tech with access to machines (last time we both sent a box to the lab and set up a temporary account in the intranet for them) || || || ||
| |
| |-
| |
| | M6 || Internal QA of docs || M2-M5 || 1 week || all ||
| |
| |-
| |
| | M7 || Communication between NSS team / Lab / NIST about status of validation / algorithm certificates || M1-5 || 3-6 mos || all ||
| |
| |}
| |
|
| |
|