== Example Timeline and Intake Phases ==
== Example Timeline and Intake Phases ==
* One month before quarter begins, mozpm sends email to all@ announcing "project submissions will start in two weeks, so start planning."
* Over the next two weeks product owners, project/program managers, and leaders from the entire organization work with their teams to hone their project list and priorities.
* Two weeks before quarter begins, mozpm sends email with link to the submission form, announcing that the window for submissions has begun and will end the day before quarter begins.
* Product owners, project/program managers, and leaders from the entire organization have a two-week window to submit their projects.
* First day of the quarter, mozpm sorts and organizes the results of the form submissions in a Google Doc spreadsheet.
* mozpm removes duplicate projects and cleans up submitted data. 2-3 days
* mozpm communicates to the organization the summaries and metrics of the submitted data by end of week.
* (Steering committee? Directors?) perform a [[Project_Management/2011_Q4/Meetings/Background_Info#Project_Prioritization|project prioritization]] process on the submitted projects. 2 days.
* (Steering committee? Directors?) review and adjust the list of projects that should be priority for the next quarter. 2 days.
* Gather feedback from all Mozilla groups if all priority projects are technically possible within the defined period of time.
* Adjust priorities based on what is possible given all of the internal constraints and feedback.