Program Management/Weekly-Status-Reports/2012-02-19: Difference between revisions

Jump to navigation Jump to search
Line 20: Line 20:


==Marco==
==Marco==
* '''Iteration #2 Update:'''
** Remaining days in iteration = 3
** Points closed to date = 18
** Stories closed/verified to date = 3
** Reopened Stories:  4
** Priority 1 Change/Defect Stories:  1
** Remaining points in iteration = 97
* '''Performance To Date:'''
** Confirmed Story Backlog:  19 ready for upcoming iterations.
** Legacy Stories:  12 remaining for QA testing (originally totalled 37).
** On Hold Stories:  6 remaining for Product Manager clarification before being moved into Story Backlog.
** Triage Work:  16 items for Product Manager to review before being converted to Defects.
** Stories to be Planned:  26 stories for Team to review, relate work items to them and assign point values.
* '''Updates:'''
** As each story is completed it is submitted to QA for funtionality testing.
** Last week the team had completed 7 stories totalling 40 story points.
*** The Team had completed more points at the half-way point of Iteration #2 than all of Iteration #1.
** 4 of the 7 stories had quality issues and were reopened reducing our story point completion count to 18.
** This follows our 'Definition of Done' to ensure the project does not collect any 'technical debt' moving forward.
*** [https://wiki.mozilla.org/Firefox/Metro#Definition_of_Done_.28DOD.29 View Metro DOD]