* '''Iteration #2 Update:''' | |||
** Remaining days in iteration = 3 | |||
** Points closed to date = 18 | |||
** Stories closed/verified to date = 3 | |||
** Reopened Stories: 4 | |||
** Priority 1 Change/Defect Stories: 1 | |||
** Remaining points in iteration = 97 | |||
* '''Performance To Date:''' | |||
** Confirmed Story Backlog: 19 ready for upcoming iterations. | |||
** Legacy Stories: 12 remaining for QA testing (originally totalled 37). | |||
** On Hold Stories: 6 remaining for Product Manager clarification before being moved into Story Backlog. | |||
** Triage Work: 16 items for Product Manager to review before being converted to Defects. | |||
** Stories to be Planned: 26 stories for Team to review, relate work items to them and assign point values. | |||
* '''Updates:''' | |||
** As each story is completed it is submitted to QA for funtionality testing. | |||
** Last week the team had completed 7 stories totalling 40 story points. | |||
*** The Team had completed more points at the half-way point of Iteration #2 than all of Iteration #1. | |||
** 4 of the 7 stories had quality issues and were reopened reducing our story point completion count to 18. | |||
** This follows our 'Definition of Done' to ensure the project does not collect any 'technical debt' moving forward. | |||
*** [https://wiki.mozilla.org/Firefox/Metro#Definition_of_Done_.28DOD.29 View Metro DOD] | |||
==Sheila== | ==Sheila== | ||