= Milestones = | = Milestones = | ||
By the end of the quarter, we want to update the code review UI on bugzilla to make it more modern and feature comparable with our competitors, complete and deploy the tracking flags optimization & migration, complete and deploy the native REST API optimization | |||
== Milestone 1 == | == Milestone 1 Tentative Dates: April 1 - April 12 == | ||
* Release plan for user workflows | |||
* Complete Tracking flags work, plan for migration | |||
* Perform first step of updates for code review functionality in bugzilla | |||
== Milestone 2 == | == Milestone 2 Tentative Dates: April 15 - April 26 == | ||
* Deploy migration for tracking flags | |||
* Complete native REST API integration work | |||
* Begin Bugzilla profile low level integration | |||
* Complete Bugzilla profile HTML Mocks | |||
* Continued work on code review changes | |||
== Milestone 3 == | == Milestone 3 Tentative Dates: April 29 - May 9 == | ||
* Wire Bugzilla profile mocks into true frontend | |||
* Delpoy native REST changes | |||
* Deploy Code Review changes | |||