Confirmed users
4,174
edits
m (→Firefox Metro) |
m (→Firefox Metro) |
||
| Line 17: | Line 17: | ||
<p> </p> | <p> </p> | ||
'''Project Management''' | '''Project Management''' | ||
* Develop a revised Metro Software Requirements Specification outlining a new version of the Minimum Viable Product (MVP) feature set. | * '''{{done|}}''' Develop a revised Metro Software Requirements Specification outlining a new version of the Minimum Viable Product (MVP) feature set. | ||
** | ** Completed at the end of Iteration #5 on April 16. Product Manager review of V1 Release List resulted in the removal of 9 Feature Stories to V2. | ||
* Conduct a review of the Story Backlog and revise the priority levels of feature stories. | * '''{{done|}}''' Conduct a review of the Story Backlog and revise the priority levels of feature stories. | ||
** | ** At the conclusion of Iteration #6, the Product Manager revised the priority levels of the feature stories in the Story Backlog. The revision resulted in: | ||
*** 30 feature stories shifted to a P1 priority level. | *** 30 feature stories shifted to a P1 priority level. | ||
*** 1 feature story shifted to a P2 priority level. | *** 1 feature story shifted to a P2 priority level. | ||
| Line 26: | Line 26: | ||
*** 12 feature stories shifted to a P4 priority level. | *** 12 feature stories shifted to a P4 priority level. | ||
* '''{{done|}}''' Develop a Pessimistic, Optimistic and Expected Release Scenario. The initial figures will be presented following the conclusion of Iteration #6 and will be updated at the conclusion of each upcoming iteration. | * '''{{done|}}''' Develop a Pessimistic, Optimistic and Expected Release Scenario. The initial figures will be presented following the conclusion of Iteration #6 and will be updated at the conclusion of each upcoming iteration. | ||
** | ** At the end of Iteration #6, the Metro project had enough performance data to establish the three release scenarios: | ||
*** Pessimistic Release Scenario - March 20, 2014: The average velocity figure of the '''worst 3 iterations is 32'''. If the team drops to this velocity figure, then development would be completed no earlier than '''19 iterations on March 20, 2014'''. | *** Pessimistic Release Scenario - March 20, 2014: The average velocity figure of the '''worst 3 iterations is 32'''. If the team drops to this velocity figure, then development would be completed no earlier than '''19 iterations on March 20, 2014'''. | ||
*** Optimistic Release Scenario - October 02, 2013: The average velocity figure of the '''best 3 iterations is 71'''. If this velocity figure can be achieved and maintained, then development would be completed no later than '''9 iterations on October 02, 2013'''. | *** Optimistic Release Scenario - October 02, 2013: The average velocity figure of the '''best 3 iterations is 71'''. If this velocity figure can be achieved and maintained, then development would be completed no later than '''9 iterations on October 02, 2013'''. | ||
| Line 33: | Line 33: | ||
* Maintain 'planning' backlog at no more than 10 items at the conclusion of Q2. | * Maintain 'planning' backlog at no more than 10 items at the conclusion of Q2. | ||
* '''{{done|}}''' Calculate a 90% confidence interval around the median velocity using a Binomial distribution. The initial figure representing the velocity range will be presented following the conclusion of Iteration #5 and will be updated at the conclusion of each upcoming iteration. | * '''{{done|}}''' Calculate a 90% confidence interval around the median velocity using a Binomial distribution. The initial figure representing the velocity range will be presented following the conclusion of Iteration #5 and will be updated at the conclusion of each upcoming iteration. | ||
** | ** At the conclusion of Iteration #5, for velocity values of 30,32,33,63,75, the Metro Team has a median velocity of 33 and there is a 90% likelihood that the actual velocity will fall between 30 and 75. | ||
** | ** At the conclusion of Iteration #6, for velocity values of 30,32,33,63,75,74, the Metro Team has a median velocity of 48 and there is a 90% likelihood that the actual velocity will fall between 30 and 75. | ||
<p> </p> | <p> </p> | ||
'''Quality Management''' | '''Quality Management''' | ||
| Line 42: | Line 42: | ||
<p> </p> | <p> </p> | ||
'''Product Development''' | '''Product Development''' | ||
* Conclude Development Iteration #5 and Deliver Release Build to Product Manager and QA Department. | * '''{{done|}}''' Conclude Development Iteration #5 and Deliver Release Build to Product Manager and QA Department. | ||
** | ** Completed at the end of Iteration #5 on April 12. | ||
* Conclude Development Iteration #6 and Deliver Release Build to Product Manager and QA Department. | * '''{{done|}}''' Conclude Development Iteration #6 and Deliver Release Build to Product Manager and QA Department. | ||
** | ** Completed at the end of Iteration #6 on April 30. | ||
* Conclude Development Iteration #7 and Deliver Release Build to Product Manager and QA Department. | * Conclude Development Iteration #7 and Deliver Release Build to Product Manager and QA Department. | ||
* Conclude Development Iteration #8 and Deliver Release Build to Product Manager and QA Department. | * Conclude Development Iteration #8 and Deliver Release Build to Product Manager and QA Department. | ||
<p> </p> | <p> </p> | ||
'''Team Performance''' | '''Team Performance''' | ||
* Iteration #5 - Team completes 40 points of of their committed Feature Stories. | * '''{{done|}}''' Iteration #5 - Team completes 40 points of of their committed Feature Stories. | ||
** | ** At the conclusion of Iteration #5 the team has surpassed the goal and completed 75 story points. | ||
* Iteration #6 - Team completes 45 points of of their committed Feature Stories. | * '''{{done|}}''' Iteration #6 - Team completes 45 points of of their committed Feature Stories. | ||
** | ** At the conclusion of Iteration #6 the team has surpassed the goal and completed 74 story points. | ||
* Iteration #7 - Team completes 50 points of of their committed Feature Stories. | * Iteration #7 - Team completes 50 points of of their committed Feature Stories. | ||
* Iteration #8 - Team completes 55 points of of their committed Feature Stories. | * Iteration #8 - Team completes 55 points of of their committed Feature Stories. | ||