Program Management/Firefox/2013-Q2-Goals: Difference between revisions

Jump to navigation Jump to search
Line 34: Line 34:
*** Optimistic Release Scenario The average velocity figure of the '''best 3 iterations is 72'''.  If this velocity figure can be achieved and maintained, then development would be completed no later than '''8 iterations on October 02, 2013'''.   
*** Optimistic Release Scenario The average velocity figure of the '''best 3 iterations is 72'''.  If this velocity figure can be achieved and maintained, then development would be completed no later than '''8 iterations on October 02, 2013'''.   
*** Expected Release Scenario - The average velocity figure from '''all the previous iterations is 54'''.  If this velocity figure can be maintained, then development would be completed in '''11 iterations on November 19, 2013'''.  
*** Expected Release Scenario - The average velocity figure from '''all the previous iterations is 54'''.  If this velocity figure can be maintained, then development would be completed in '''11 iterations on November 19, 2013'''.  
** At the end of Iteration #8, the three release scenarios were as follows:
*** Pessimistic Release Scenario - The average velocity figure of the '''worst 3 iterations is 32'''.  If the team drops to this velocity figure, then development would be completed no earlier than '''18 iterations on March 20, 2014'''. 
*** Optimistic Release Scenario The average velocity figure of the '''best 3 iterations is 72'''.  If this velocity figure can be achieved and maintained, then development would be completed no later than '''8 iterations on October 02, 2013'''. 
*** Expected Release Scenario - The average velocity figure from '''all the previous iterations is 53'''.  If this velocity figure can be maintained, then development would be completed in '''11 iterations on November 19, 2013'''.
* Maintain 'triage' backlog at no more than 10 items at the conclusion of Q2.
* Maintain 'triage' backlog at no more than 10 items at the conclusion of Q2.
* Maintain 'planning' backlog at no more than 10 items at the conclusion of Q2.
* Maintain 'planning' backlog at no more than 10 items at the conclusion of Q2.