Program Management/Firefox/2013-Q2-Goals: Difference between revisions

Jump to navigation Jump to search
Line 38: Line 38:
*** Optimistic Release Scenario The average velocity figure of the '''best 3 iterations is 72'''.  If this velocity figure can be achieved and maintained, then development would be completed no later than '''8 iterations on October 02, 2013'''.   
*** Optimistic Release Scenario The average velocity figure of the '''best 3 iterations is 72'''.  If this velocity figure can be achieved and maintained, then development would be completed no later than '''8 iterations on October 02, 2013'''.   
*** Expected Release Scenario - The average velocity figure from '''all the previous iterations is 53'''.  If this velocity figure can be maintained, then development would be completed in '''11 iterations on November 19, 2013'''.  
*** Expected Release Scenario - The average velocity figure from '''all the previous iterations is 53'''.  If this velocity figure can be maintained, then development would be completed in '''11 iterations on November 19, 2013'''.  
** At the end of Iteration #9, the three release scenarios were as follows:
*** Pessimistic Release Scenario - With a velocity performance of 32 development would be completed no earlier than 17 iterations on March 06, 2014. 
*** Optimistic Release Scenario - With a velocity performance of 74 development would be completed no later than 8 iterations on October 22, 2013. 
*** Expected Release Scenario - With a velocity performance of 51 development would be completed in 11 iterations on December 05, 2013.
* Maintain 'triage' backlog at no more than 10 items at the conclusion of Q2.
* Maintain 'triage' backlog at no more than 10 items at the conclusion of Q2.
* Maintain 'planning' backlog at no more than 10 items at the conclusion of Q2.
* Maintain 'planning' backlog at no more than 10 items at the conclusion of Q2.
Confirmed users
4,174

edits

Navigation menu