Milestone 5 - 2 weeks (June 24 - July 5)
* (ongoing) [mdas] Resolve blocking issues with tap
* [mdas] Resolve blocking scroll issues
* (ongoing) [mdas] {{done|Add }} some mechanisms to make debugging touch related problems easier* [jgriffin] {{ok|Disable }} gaia-unit-tests that are still failing on cedar* [jgriffin + releng] {{miss|Get }} gaia-unit-tests scheduled on all branches (depends on gecko-gaia coupling)* [jgriffin] {{done|Update {{ mozharness script for gaia-ui-tests* [jgriffin + releng] {{miss|Get }} gaia-ui-tests on b2g desktop builds scheduled on cedar (depends on gecko-gaia coupling, gaia-ui-tests to gaia coupling, and gaia-ui-tests branch renaming)* [jgriffin] {{defer|Identify }} current B2G top oranges* [ahal] {{ok|Identify }} and fix issues with full-stack emulator builds
* [rwood] Fix intermittent gaia-ui endurance test failures
* [rwood] Expand gaia-ui endurance test coverage
Confirm
1,905
edits

Navigation menu