Goal 2013 Q3
* ongoing - patches in hand - [ahal] Add mach to B2G so we can build B2G mach targets
* scheduled on cedar - [mihnea] Get JSreftests working for B2G
* (carry over) [jgriffin] {{done|Implement }} script to compare two sources.xml
* {{done|final patch up}} - (carry over) [mdas] Implement modal dialog support in Marionette
* current focus -> (carry over) [mdas] Fix remaining blocking touch issues
* [rwood] Create app-launch and page-browser tsets for AWSY
* (carry over) [rwood] Look into data requirements for gaia-ui heuristics
 
== Milestone 8 - 2 weeks (August 19 - August 30) ==
* (carry over) [ahal] Add mach to B2G so we can build B2G mach targets
* {{done|scheduled}} on cedar - [mihnea] Get JSreftests working for B2G
* P1! [jgriffin + all] Update all testing docs to make it easy for developers to get started with tests
* [mdas] Investigate modal dialog test failure
* (carry over) [rwood] Get games benchmarking tests running on Firefox OS
* (ongoing) [rwood] {{ok|Investigate/fix}} intermittent WebAPI emulator failures
* (ongoing) [rwood] Maintain endurance tests as needed (Leo on v1-train); expand checks for b2g memory changes over time
* currently working with jlebar on this -> [rwood] Validate emulator as platform for AreWeSlimYet (AWSY) memory tests
* [rwood] Create app-launch and page-browser tsets for AWSY
== Future milestones ==
* Look into data requirements for gaia-ui heuristics
* {{drop|Gaia}} bisection tool - implemented by jhford
* Make B2G tests in TBPL more sheriffable, by providing a tool in TBPL (Treeherder?) to compare revisions of all B2G repos between arbitrary builds