The following proposed schedule assumes no re-spin. | The following proposed schedule assumes no re-spin. | ||
* | * en-US string freeze: January 25 (any changes after this date need late-l10n keyword on the bug) | ||
* Code freeze: January 29 | * Code freeze: January 29 | ||
* Build starts: February 4 | * Build starts: February 4 | ||
* QA/Testing starts: February 4/5 | * QA/Testing starts: February 4/5 | ||
* Final release: 1.5 weeks later (or so) | * Final release: 1.5 weeks later (or so) | ||