| == Timeline == | | == Timeline == |
| === Release ===
| |
| * Day 0 (Tuesday)
| |
| ** Release Management migrates the mozilla-beta branch to mozilla-release
| |
| ** Automation Development migrates the mozmill-tests mozilla-beta branch to mozilla-release
| |
| ** Release Management sends the go-to-build for the first Release Candidate
| |
| ** Release Engineering generates the builds (takes several hours)
| |
| * Day 1 (Wednesday)
| |
| ** QA develops a Release test plan including manual regression tests and bug fix verifications, then coordinates overnight testing of the Release Candidates via email to Softvision
| |
| * Day 2 (Thursday)
| |
| ** QA runs Mozmill-Ondemand functional automation, update automation on the ''betatest'' channel
| |
| ** QA coordinates further overnight testing of the Release Candidates via email to Softvision
| |
| * Day 3 (Friday)
| |
| ** QA coordinates further overnight testing of the Release Candidates via email to Softvision
| |
| * Day 6 (Monday)
| |
| ** QA sends conditional sign-off of the Release Candidates via email to the Release Drivers
| |
| ** Release Management sends the go to push snippets to mirrors
| |
| ** Release Engineering pushes Release Candidate snippets to mirrors and sends email to Release Drivers when complete
| |
| ** QA runs Mozmill-Ondemand update automation on the ''releasetest'' channel
| |
| * Day 7 (Tuesday)
| |
| ** QA sends final sign-off for release via email to the Release Drivers
| |
| ** Release Management sends the go to push snippets live
| |
| ** Release Engineering pushes Release Candidate snippets live and sends email to the Release Drivers when complete
| |
| ** QA runs Mozmill-ondemand update automation on the ''release'' channel then sends a sign-off email to Release Drivers when complete
| |
| ** Release Management pushes web content
| |
| ** WebQA verifies web content is live
| |
| ** RRRT creates a page to track potential .point release issues
| |
| * Day 8+
| |
| ** QA assists with investigating any potential point release issues and prepares test plans for point releases as required
| |
| * Day 41 (Monday)
| |
| ** Point of no return for any point releases
| |
| * Day 42 (Tuesday)
| |
| ** Release Management migrates mozilla-beta to mozilla-release and sends the go to build the next Release
| |
|
| |
| === ESR === | | === ESR === |
| * Day 0..36 | | * Day 0..36 |