Stub Installer Deployment

  • Feature Name: Firefox Desktop Stub Installer
  • Problem/Opportunity Statement: Increase download to install conversions
  • Impact on Mozilla Goals: Positive impact on ADI growth
  • Release Timing: ASAP in October
  • Key Requirements for Delivery:
    • a ~200kb Windows downloader app that wraps our existing installer deployed with sufficient testing to minimize risk to new users (scope of original feature)
    • streamlined Installer user flow
    • dynamic marketing channel inside of the stub/downloader
    • deployed with sufficient measurements to determine efficacy
  • Current Status: Stub Installer development, including expanded scope items, completed. Testing, deployment, and measurement still pending.
  • Resources Required:
    • Product Management - Asa Dotzler
    • Firefox UX - Madhava Enros
    • Firefox Platform Integration Engineering - Rob Strong
    • L10N - Axel Hecht
    • Firefox QA - Jason Smith
    • Release Engineering - Chris Atlee
    • IT Systems Team - Corey Shields
    • Web Operations - Jake Maul
    • Web Productions - Chris More
    • Website QA -
    • Metrics Team - Gilbert FitzGerald
    • Release Management - Alex Keybl
    • Project Management - Melissa O'Connor

Meeting Notes

10/1/12 Meeting Notes:

  • Engineering & QA Update / Rob Strong and Jason Smith
    • Engineering - Release is ready for QA
    • QA - Test plan is ready to go, Jason just needs the information on the location of the release. 1-3 days of testing
    • Test the build, today/tomorrow to verify functionality. Then work to get it manually signed.
  • Metrics Testing Plan / Anurag & Gilbert
    • 2-3 days, if this looks good, they will do a 3 day full test on Thurs, Friday and Saturday on beta/aurora.
    • Phase 2 would involve a 90/10 split.
  • Mozillians Communication Plan / Laura F.
    • Working on a communication that will go to the mozillians list, a call for action to test. Feedback will go to an email group that is being setup.

Action Items from 9/28 meeting:

  • Anurag to generate a new metrics proposal by end of day Friday
  • Johnathan to find an owner for funnel cake bug 774618
  • Paxton and Laura to work on documenting the deployment channel permutations
  • Corey/Laura/Jake to generate a deployment and test plan for stub install by end of day Friday - sent out Friday
  • Laura (Product Marketing) to generate a communications plan to Mozillians asking for help in testing the stub installer - Done