Websites/Affiliates Facebook App/Weekly-Status-Reports/2012-06-21

From MozillaWiki
Jump to: navigation, search
Summary
DOC VERSION: 1.0 STATUS REPORT AS OF: June 21 2012
AUTHOR: Benjamin Sternthal
TPM: Benjamin Sternthal
PROJECT SPONSOR: Chelsea Novak
PROJECT WIKI: Websites/Affiliates_Facebook_App
Status
1. STATUS
Status Item On Track Caution Crisis N/A Comment
OVERALL STATUS X
Schedule X
Scope X
Budget X
Schedule & Budget
2. SCHEDULE
Start Date Completion Date
Original Current Original Current
June 11 June 11 TBD
3. BUDGET
Original Current
Cost Of Work
Performed
Estimated
Actual Cost
Variance
at
Completion
N/A N/A N/A N/A
Recent Accomplishments
4. RECENT ACCOMPLISHMENTS
  • Wireframes .1 completed
  • Lots of facebook/facebook ad api investigations
Upcoming Tasks
5. UPCOMING TASKS
Task Owner Due Date Bugzilla Comments
Finalize Wireframes BS/Team Complete
Major Issues
6. MAJOR ISSUES, CONCERNS & IMPACTS (* = new)
Issue Description Owner Priority Date Due Bugzilla Status
Decide On Pursuing Ad API* High 6/25 In Progress
Project Milestones
7. PROJECT MILESTONES
Issue Owner Target
Completion
Date
Revised
Completion
Date
Actual
Completion
Date
Bugzilla Status
WebDev
   Wireframes Final BS Complete
   Ready To Test MK TBD
   Live MK TBD
Design
   Deliverable 1 TBD TBD
Privacy/Legal
   Review TBD TBD
QA
   Review TBD TBD
Security
   Review TBD TBD