Websites/Affiliates Facebook App/Weekly-Status-Reports/2012-07-11
From MozillaWiki
Contents
Summary
DOC VERSION: 1.0 | STATUS REPORT AS OF: July 11 2012 |
AUTHOR: Benjamin Sternthal |
TPM: Benjamin Sternthal |
PROJECT SPONSOR: Chelsea Novak |
PROJECT WIKI: Websites/Affiliates_Facebook_App |
Status
1. STATUS | |||||
Status Item | On Track | Caution | Crisis | N/A | Comment |
OVERALL STATUS | X | ||||
Schedule | X | ||||
Scope | X | ||||
Budget | X |
Schedule & Budget
2. SCHEDULE | |||
Start Date | Completion Date | ||
Original | Current | Original | Current |
June 11 | June 11 | 8/29 |
3. BUDGET | |||
Original | Current Cost Of Work Performed |
Estimated Actual Cost |
Variance at Completion |
N/A | N/A | N/A | N/A |
Recent Accomplishments
4. RECENT ACCOMPLISHMENTS |
|
Upcoming Tasks
5. UPCOMING TASKS | ||||
Task | Owner | Due Date | Bugzilla | Comments |
Copy Deck | CN/BS | 7/18 | ||
Ad Prototype | Matt/CN | |||
Design Scope/Hours | Team/Matt | |||
L10N Plan | BS/Milos |
Major Issues
6. MAJOR ISSUES, CONCERNS & IMPACTS (* = new) | |||||||
Issue Description | Owner | Priority | Date Due | Bugzilla | Status | ||
Project Milestones
7. PROJECT MILESTONES | |||||||
Issue | Owner | Target Completion Date |
Revised Completion Date |
Actual Completion Date |
Bugzilla | Status | |
WebDev | |||||||
Wireframes Final | BS | 7/5 | Complete | ||||
Ready To Test | MK | 8/17 | |||||
Live | MK | 8/29 | |||||
Creative | |||||||
Ad Prototype | CN/Matt | TBD | |||||
5 Ads Spec'd | CN | TBD | |||||
Copy Final | CN | TBD | 773030 | ||||
Design | |||||||
Designs 1st Round | Matt | TBD | |||||
Designs Final | Matt | TBD | |||||
Privacy/Legal | |||||||
Initial Review | SM | 7/9 | Complete | ||||
TOS/PP/FAQ Review | SM | 7/30 | |||||
L10N | |||||||
L10N Start | MD | TBD | |||||
L10N Complete | MD | TBD | 772251 | ||||
QA | |||||||
Review | RB | 8/17 - 8/24 | 772284 | ||||
Security | |||||||
Review | TBD | 8/17 - 8/24 | 772287 | ||||
IT | |||||||
FB Dev Server | JD | 7/13 | 772183 |