| DOC VERSION: 1.0 | STATUS REPORT AS OF: June 15, 2012 |
| AUTHOR: Benjamin Sternthal |
| TPM: Benjamin Sternthal |
| PROJECT SPONSOR: Winston Bowden |
| PROJECT WIKI: Websites/Snippets/Impressions |
Status
| 1. STATUS | |||||
| Status Item | On Track | Caution | Crisis | N/A | Comment |
| OVERALL STATUS | X | ||||
| Schedule | X | ||||
| Scope | X | ||||
| Budget | X | ||||
Schedule & Budget
| 2. SCHEDULE | |||
| Start Date | Completion Date | ||
| Original | Current | Original | Current |
| Jan 20 | Jan 20 | March 7 | June 18 |
| 3. BUDGET | |||
| Original | Current Cost Of Work Performed |
Estimated Actual Cost |
Variance at Completion |
| N/A | N/A | N/A | N/A |
Recent Accomplishments
| 4. RECENT ACCOMPLISHMENTS |
|
Upcoming Tasks
| 5. UPCOMING TASKS | ||||
| Task | Owner | Due Date | Bugzilla | Comments |
| Update Privacy Policy | Schalk Neethling sneethling@mozilla.com | 6/15 | 764151 | |
| Launch JS | Mkelly | 6/18 | ||
Major Issues
| 6. MAJOR ISSUES, CONCERNS & IMPACTS (* = new) | |||||||
| Issue Description | Owner | Priority | Date Due | Bugzilla | Status | ||
| Data Safety Approval * | David Ascher | Block | 723589 | Complete | |||
| Privacy Policy Approval | Tom L | 761818 | Complete | ||||
| Governance Review | Governance | Complete | |||||
Project Milestones
| 7. PROJECT MILESTONES | |||||||
| Issue | Owner | Target Completion Date |
Revised Completion Date |
Acutal Completion Date |
Bugzilla | Status | |
| WebDev | |||||||
| JS | MK | 4/13 | 4/12 | 690881 | Complete | ||
| Admin Interface | MK | 4/20 | 4/12 | 743822 | Complete | ||
| Launch | MK/JM | 4/30 | 4/23 | ||||
| Privacy | |||||||
| Review Collection Data | AH | 6/12 | 723589 | Complete | |||
| Security | |||||||
| Security Review | YB | 4/16 - 4/18 | 4/20 | 723596 | Complete | ||
| QA | |||||||
| QA Review | SD | 4/16 - 4/19 | 4/20 | 723600 | Complete | ||
| IT | |||||||
| Setup Server(s) | JM | 3/16 | 4/6 | 4/6 | 698815 | Complete | |
| SSL Cert | JM | 4/6 | 4/6 | 740959 | Complete | ||
| Metrics | |||||||
| Stage Dashboard Basic nightly email report detailing impressions and clicks, campaign-id |
AP | 4/30 | |||||