(Created page with "__NOTOC__ <big><big><big>'''Status Report for Firefox on iOS for the period of 14/10/2015 - 21/10/2015'''</big></big></big> == Overall Project Health == {| cellpadding="10" !...") |
|||
Line 23: | Line 23: | ||
<!--Should explain WHY for the health/status reported above. Items covered here may be covered in more detail further down in the report. If senior management were to look at nothing but this section, they should be able to tell what is going on with the project.--> | <!--Should explain WHY for the health/status reported above. Items covered here may be covered in more detail further down in the report. If senior management were to look at nothing but this section, they should be able to tell what is going on with the project.--> | ||
* V1.1 Build #12 was released this morning - this is our 4th potential RC build. The team continues to fix reported issues and crashers to get things as stable as possible. | * V1.1 Build #12 was released this morning - this is our 4th potential RC build. The team continues to fix reported issues and crashers to get things as stable as possible. | ||
* [https://l10n.mozilla-community.org/~flod/webstatus/?product=firefox-ios Locales] - 44 Completed, but final | * [https://l10n.mozilla-community.org/~flod/webstatus/?product=firefox-ios Locales] - 44 Completed, but final count for launch is 43. | ||
== Risks & Issues == | == Risks & Issues == |
Latest revision as of 15:40, 21 October 2015
Status Report for Firefox on iOS for the period of 14/10/2015 - 21/10/2015
Overall Project Health
This Week | Last Week |
---|---|
Exec Summary/Hot Topics
- V1.1 Build #12 was released this morning - this is our 4th potential RC build. The team continues to fix reported issues and crashers to get things as stable as possible.
- Locales - 44 Completed, but final count for launch is 43.
Risks & Issues
Description of Risk/Issue | State | Owner | Plan to Resolve/Mitigation | Target Date |
---|---|---|---|---|
Resourcing constraints | CLOSED | Jenn/Eng Mgt | The team is smaller by 1.5 full-time, plus 1 intern, compared to V1.0 resourcing. Scope and resource allocation will be monitored closely throughout the project. | No need to monitor further for V1.1 |
Timeline constraints | CLOSED | Jenn/Eng Mgt | Development timelines required to deliver must-have features are very tight. No scope creep can be permitted, and progress to be monitored closely. Any 'nice-to'have' features that did not meet string freeze will not be considered for the release. | No need to monitor further for V1.1 |
Accomplished for the Last Period
- Multiple V1.1 builds released to internal aurora and external test flight
- L10N Frozen - 10/19
- Team working on final fixes/crashes in preparation for submission
Planned for Last Period but Not Accomplished
- N/A
Planned for the Upcoming Period
- V1.1 Builds and testing to continue
- Blog Post ready for final approval - Postponed to 10/20 ; awaiting confirmation this was completed
- Store fields/screenshots updated and ready for submission