SFx redesign timeline: Difference between revisions

From MozillaWiki
Jump to navigation Jump to search
No edit summary
Line 4: Line 4:


= January 2009 =
= January 2009 =
Redesign:
* Jan. 12th:  Neil to splice PSDs and create CSS/HTML  
* Jan. 12th:  Neil to splice PSDs and create CSS/HTML  
* Jan. 26th:  CSS/HTML implemented in SFX codebase/site staged
* Jan. 26th:  CSS/HTML implemented in SFX codebase/site staged
* Jan. 28th:  Marketing to provide feedback
* Jan. 28th:  Marketing to provide feedback
* Jan. 30th:  Alex to complete [https://wiki.mozilla.org/SFx_homepage_requirements#Admin_Interface_needs_for_News_.26_Events_page P1 admin needs] for new SFx
* Jan. 30th:  Alex to complete [https://wiki.mozilla.org/SFx_homepage_requirements#Admin_Interface_needs_for_News_.26_Events_page P1 admin needs] for new SFx
Drupal Migration:
* Jan. 9th: 
** Alex to file a bug to get a staging server up
* Jan. 16th: 
** Mary, Paul and team to resolve Varbinary issue
** Alex to get staging server set up (is this an IT issue?)
* Jan. 19th:  Get Sfx database copied over (is this still needed?)


= February 2009 =
= February 2009 =
* Feb. 4th:  Site iterations complete/QA kicks off
 
Redesign:
* Feb. 4th:  Site iterations complete
 
Drupal Migration:
* Feb. 9th:  Finish new theme
 
= March 2009 =
 
* March 2nd: Site QA kicks off
* March 23rd:  New site live
 
* Feb. 16th:  Site live
* Feb. 16th:  Site live

Revision as of 00:58, 7 January 2009

December 2008

  • Dec. 5: Mary to hand off final files (done)
  • Dec. 31: Neil to splice PSDs and create CSS/HTML (moved to Jan)

January 2009

Redesign:

  • Jan. 12th: Neil to splice PSDs and create CSS/HTML
  • Jan. 26th: CSS/HTML implemented in SFX codebase/site staged
  • Jan. 28th: Marketing to provide feedback
  • Jan. 30th: Alex to complete P1 admin needs for new SFx

Drupal Migration:

  • Jan. 9th:
    • Alex to file a bug to get a staging server up
  • Jan. 16th:
    • Mary, Paul and team to resolve Varbinary issue
    • Alex to get staging server set up (is this an IT issue?)
  • Jan. 19th: Get Sfx database copied over (is this still needed?)

February 2009

Redesign:

  • Feb. 4th: Site iterations complete

Drupal Migration:

  • Feb. 9th: Finish new theme

March 2009

  • March 2nd: Site QA kicks off
  • March 23rd: New site live
  • Feb. 16th: Site live