MDN/Archives/Dev Milestones: Difference between revisions
Jump to navigation
Jump to search
Line 25: | Line 25: | ||
* Meetings | * Meetings | ||
** [https://etherpad.mozilla.org/vPkLTlmLQK Planning and retrospective] | ** [https://etherpad.mozilla.org/vPkLTlmLQK Planning and retrospective] | ||
** [https://etherpad.mozilla.org/review-2012-07-13 | ** [https://etherpad.mozilla.org/review-2012-07-13 Review and feedback] | ||
* Artifacts | * Artifacts | ||
** [http://scrumbu.gs/projects/mdn/2012-07-15/ Sprint backlog] | ** [http://scrumbu.gs/projects/mdn/2012-07-15/ Sprint backlog] |
Revision as of 23:29, 18 July 2012
Product backlog (running list of all remaining work)
Timeline
- 8-Jun - general testing period starts
- 21-30 June - general testing - edit & add content (wiki pages, files, code samples)
- 7-8 July - bug hunt with Mozilla QA
- 10-July - deki shut off for updates (browse only) - final content migration, link to kuma "beta" for browsing
- 10-15 July - writing/editing on kuma, continue testing, verify bug fixes
- 16-July - cutover
Development Sprints
The Kuma development team is using the Scrum method of agile software development. Our sprints are two weeks and code is pushed weekly. See below for details on what bugs are addressed in each sprint.
Sprint ending July 17, 2012
- Meetings
- Artifacts
Sprint ending July 15, 2012
- Meetings
- Artifacts
Sprint ending 03-July-2012
- Meetings
- Artifacts