FirefoxOS/DeviceQA/2015-09-21WeeklyReport: Difference between revisions
Jump to navigation
Jump to search
No edit summary |
No edit summary |
||
(12 intermediate revisions by 12 users not shown) | |||
Line 10: | Line 10: | ||
|| | || | ||
* Week W38 (09/14~09/18) | * Week W38 (09/14~09/18) | ||
** [v2.5 Pin the Web] Update test cases and prepare test data(web app) after get developers feedback | |||
** [v2.5 Pin the Web] Update test plan with new promised features | |||
** [v2.5 Pin the Web] Add test cases for task manager enhancement | |||
** [v2.5 Tracking Protection] Study Tracking Protection in Firefox Browser(desktop) | |||
** Bugs work from QAnalyst/Marigold | |||
|| | || | ||
* Week W39 (09/21~09/25) | * Week W39 (09/21~09/25) | ||
** [v2.5 Pin the Web] Update test plan and test cases based on the latast UX spec | |||
** [v2.5 Tracking Protection] Study feature and write test plan | |||
** Bugs work from QAnalyst/Marigold | |||
|- | |- | ||
|Askeing | |Askeing | ||
|| | || | ||
* Week W38 (09/14~09/18) | * Week W38 (09/14~09/18) | ||
** Investigate the Mocha, Chai, Karma and node.js | |||
** Prepare Slides of Academy Program | |||
** Prepare the homework on github (using Travis) | |||
|| | || | ||
* Week W39 (09/21~09/25) | * Week W39 (09/21~09/25) | ||
** Prepare Slides of Academy Program | |||
** Investigate the biwet issue | |||
** Develop the prototype of TC DL | |||
|- | |- | ||
| Cynthia | | Cynthia | ||
|| | || | ||
* Week W38 (09/14~09/18) | * Week W38 (09/14~09/18) | ||
** [v2.5 TV - Firefox Account] Design test plan and test cases | |||
** [v2.5 TV - Browser] Execute the testing | |||
** [v2.5 TV - EPG] Design test plan | |||
** [v2.5 TV] Bugs work | |||
|| | || | ||
* Week W39 (09/21~09/25) | * Week W39 (09/21~09/25) | ||
** [v2.5 TV - TV Deck] Design test cases and execute the testing | |||
** [v2.5 TV - EPG] Design test cases and execute the testing | |||
** [v2.5 TV] Bugs work | |||
|- | |- | ||
|Gerry | |Gerry | ||
|| | || | ||
* Week W38 (09/14~09/18) | * Week W38 (09/14~09/18) | ||
** v2.5 feature planning | |||
*** Feature clarification/assignment | |||
*** Marigold issues support | |||
*** 2.5 bugs triage/Stagnant issue check | |||
*** Data Sync/TV Firefox Account knowledge sharing | |||
*** Bugzilla lite - create exploratory/negative test cases | |||
*** Telemetry patches evaluation | |||
|| | || | ||
* Week W39 (09/21~09/25) | * Week W39 (09/21~09/25) | ||
** v2.5 feature planning | |||
*** Feature clarification/assignment | |||
*** Marigold issues support | |||
*** 2.5 bugs triage/Stagnant issue check | |||
*** Telemetry feature testing | |||
|- | |- | ||
|Iris | |Iris | ||
|| | || | ||
* Week W38 (09/14~09/18) | * Week W38 (09/14~09/18) | ||
** Set up New-Hires respects: install software, set up accounts | |||
** Study firefox OS | |||
*** introduction | |||
*** flash mobile | |||
*** clone github repository, reset gaia | |||
*** practice moztrap testcases: [system platform] settings: notification, keyboard, lockscreen | |||
|| | || | ||
* Week W39 (09/21~09/25) | * Week W39 (09/21~09/25) | ||
** Set up testing environment on Desktop | |||
** Practice automation testing b2g | |||
** Study ftu-ping, app usage testing | |||
|- | |- | ||
| Kinder | | Kinder | ||
|| | || | ||
* Week W38 (09/14~09/18) | * Week W38 (09/14~09/18) | ||
** [New Tool Development] | |||
*** Survey Puppet Scripts (cont.) | |||
|| | || | ||
* Week W39 (09/21~09/25) | * Week W39 (09/21~09/25) | ||
** [New Tool Development] | |||
*** Prepare Puppet Scripts demo | |||
|- | |- | ||
Line 58: | Line 94: | ||
|| | || | ||
* Week W38 (09/14~09/18) | * Week W38 (09/14~09/18) | ||
** [v2.5] | |||
*** Monitor performance regression | |||
*** Add-ons test case creation | |||
*** Study New Security Model | |||
|| | || | ||
* Week W39 (09/21~09/25) | * Week W39 (09/21~09/25) | ||
** [Open Mobile] | |||
*** P1 issues verification | |||
** [v2.5] | |||
*** Monitor performance regression | |||
*** Add more add-ons test cases | |||
*** Study New Security Model | |||
|- | |- | ||
| Paul | | Paul | ||
|| | || | ||
* Week W38 (09/14~09/18) | * Week W38 (09/14~09/18) | ||
** crash monitoring agent | |||
|| | || | ||
* Week W39 (09/21~09/25) | * Week W39 (09/21~09/25) | ||
** running crash agent in lab | |||
** integrating crash-bug-report system | |||
|- | |- | ||
| Shako Ho | | Shako Ho | ||
|| | || | ||
* Week W38 (09/14~09/18) | * Week W38 (09/14~09/18) | ||
** MTBF | |||
*** integrate the raptor Minion with boss framework [pending] | |||
*** Fix MTBF test cases on aries [in progress] | |||
|| | || | ||
* Week W39 (09/21~09/25) | * Week W39 (09/21~09/25) | ||
** MTBF | |||
*** integrate the raptor Minion with boss framework [pending] | |||
*** Fix MTBF test cases on aries [in progress] | |||
|- | |- | ||
Line 82: | Line 133: | ||
|| | || | ||
* Week W38 (09/14~09/18) | * Week W38 (09/14~09/18) | ||
** RedSquare workshop preparation | |||
** RedSquare acceptance criteria writing | |||
** Academy program course preparation | |||
|| | || | ||
* Week W39 (09/21~09/25) | * Week W39 (09/21~09/25) | ||
** RedSquare workshop at Mountain View | |||
|- | |- | ||
| Teri | | Teri | ||
|| | || | ||
* Week W38 (09/14~09/18) | * Week W38 (09/14~09/18) | ||
** [V2.5] | |||
*** Replaceable Homescreen | |||
**** New home screen | |||
***** Updated test plan with negative test cases | |||
***** Reviewed Marigold Regression Test Report | |||
****** Found regression on soft home button | |||
***** Completed memory tests using get_about_memory.py | |||
***** Sent memory test results to Dev for feedback | |||
**** Replaceable Homescreen | |||
***** Completed test plan and test cases | |||
***** Proposed homescreen development work to automation team | |||
***** Defined homescreen development requirements and added on scrumdesk | |||
** [V2.5 PTS] | |||
*** Prepare PTS required materials | |||
|| | || | ||
* Week W39 (09/21~09/25) | * Week W39 (09/21~09/25) | ||
** [V2.5] | |||
*** Replaceable Homescreen | |||
**** New home screen | |||
***** Additional tests as suggested by Dev feeback | |||
**** Replaceable homescreen | |||
***** Send out test cases and test plan for review | |||
** [V2.5 PTS] | |||
*** Review Marigold PTS test result | |||
|- | |- | ||
| Walter | | Walter | ||
|| | || | ||
* Week W38 (09/14~09/18) | * Week W38 (09/14~09/18) | ||
** PTO 9/18 | |||
** Rerun MCTS to get an overall result and try to fix | |||
*** Security passed | |||
*** WebAPI: lots of issues, clarifying with other people | |||
*** Report: didn't show actual result | |||
** PR reviews | |||
|| | || | ||
* Week W39 (09/21~09/25) | * Week W39 (09/21~09/25) | ||
** PR reviews | |||
** MCTS Cert-WebAPI fixes | |||
|- | |- | ||
| William Hsu | | William Hsu | ||
Line 109: | Line 189: | ||
*** Low application storage progress sync-up, 9/11 | *** Low application storage progress sync-up, 9/11 | ||
**** https://etherpad.mozilla.org/devicestorage | **** https://etherpad.mozilla.org/devicestorage | ||
*** L10n test case creation and review, and knowledge sharing | *** L10n test case creation and review, and knowledge sharing | ||
**** https://etherpad.mozilla.org/2-5-TestCases | **** https://etherpad.mozilla.org/2-5-TestCases | ||
*** RTL progress follow-up | *** RTL progress follow-up and discussion | ||
**** https://etherpad.mozilla.org/RTL2-5 | **** https://etherpad.mozilla.org/RTL2-5 | ||
** [Outsourcing] | ** [Outsourcing] | ||
*** Marigold weekly report ( https://goo.gl/XIQ2fy ) | *** Marigold weekly report ( https://goo.gl/XIQ2fy ) | ||
*** v2.5 task assignment ( https://goo.gl/GlRzjL ) | *** v2.5 task assignment ( https://goo.gl/GlRzjL ) | ||
*** Help trace GIP failed test cases | *** Help trace GIP failed test cases | ||
**** Smoketest: http://goo.gl/psCduI | **** Smoketest: http://goo.gl/psCduI | ||
**** Nonsmoketest: http://goo.gl/ZCPRBK | **** Nonsmoketest: http://goo.gl/ZCPRBK | ||
Line 124: | Line 203: | ||
|| | || | ||
* Week W39 (09/21~09/25) | * Week W39 (09/21~09/25) | ||
** Follow v2.5 user story | |||
*** Low application storage progress sync-up | |||
**** https://etherpad.mozilla.org/devicestorage | |||
*** Test plan - https://goo.gl/ApQlKJ | |||
*** L10n test case creation and review, and knowledge sharing | |||
**** https://etherpad.mozilla.org/2-5-TestCases | |||
*** RTL progress follow-up and discussion | |||
**** https://etherpad.mozilla.org/RTL2-5 | |||
*** 2.5 RTL spec study and deliver guideline to QA engineer | |||
** [Outsourcing] | |||
*** Marigold weekly report ( https://goo.gl/XIQ2fy ) | |||
*** v2.5 task assignment ( https://goo.gl/GlRzjL ) | |||
*** Help trace GIP failed test cases | |||
**** Smoketest: http://goo.gl/psCduI | |||
**** Nonsmoketest: http://goo.gl/ZCPRBK | |||
*** Tracing Marigold working model and process | |||
*** Follow up fullrun-2 progress and triage fullrun bugs | |||
|- | |- | ||
|} | |} |
Latest revision as of 02:57, 5 October 2015
Name | Done | Plan |
---|---|---|
Alison |
|
|
Askeing |
|
|
Cynthia |
|
|
Gerry |
|
|
Iris |
|
|
Kinder |
|
|
Mike |
|
|
Paul |
|
|
Shako Ho |
|
|
Shing |
|
|
Teri |
|
|
Walter |
|
|
William Hsu |
|
|