== Exec Summary/Hot Topics == | == Exec Summary/Hot Topics == | ||
<!--Should explain WHY for the health/status reported above. Items covered here may be covered in more detail further down in the report. If senior management were to look at nothing but this section, they should be able to tell what is going on with the project.--> | <!--Should explain WHY for the health/status reported above. Items covered here may be covered in more detail further down in the report. If senior management were to look at nothing but this section, they should be able to tell what is going on with the project.--> | ||
* The team is progressing | * The team is progressing well overall for the release. | ||
** Some additional follow-on work added to the backlog, and 3 items pending size estimates, which has affected completion rate (dropped to 49%). | |||
* Status remains Yellow due to one item remaining in blocked state - Telemetry Probes. See 'Risks & Issues' for more details. | * Status remains Yellow due to one item remaining in blocked state - Telemetry Probes. See 'Risks & Issues' for more details. | ||
Revision as of 15:37, 29 July 2015
Status Report for Fennec - Tracking Protection - for the period from 22/07/2015 - 29/07/2015
Overall Project Health
| This Week | Last Week |
|---|---|
Exec Summary/Hot Topics
- The team is progressing well overall for the release.
- Some additional follow-on work added to the backlog, and 3 items pending size estimates, which has affected completion rate (dropped to 49%).
- Status remains Yellow due to one item remaining in blocked state - Telemetry Probes. See 'Risks & Issues' for more details.
Risks & Issues
| Description of Risk/Issue | State | Owner | Plan to Resolve/Mitigation | Target Date |
|---|---|---|---|---|
| Team assigned is not 100% dedicated to Tracking Protection work, which has potential to impact ability to complete work | Open | Margaret, Jenn | Monitor how the team is doing in terms of meeting commitment for Tracking Protection, and discuss adjusting other workload as neccessary | Ongoing for the release |
| Eng is blocked on 1175977 as the list of required telemetry probes has not yet been defined | Open | Product Management | Desktop and mobile Product Management in discussion with Mobile Eng. Definition required for the list of information that is actually useful and should be measured/collected. Full audit may be necessary from the analysts, and a metrics design plan delivered. Javaun is meeting with analysts this afternoon (Wednesday). | Aug 10th |
| Eng is blocked on 1177612 as the design decisions have not yet been finalized | CLOSED | UX & Product Management | Agreement has been reached and assets provided. | July 27th |
Accomplished for the Last Period
- Decision reached to unblock work on Contextual Hint 1177612
- Discussion kicked off to work toward resolving roadblocks for Telemetry
Planned for Last Period but Not Accomplished
Planned for the Upcoming Period
Status Details
- TP-Mobile-ByBug 07-29-15.jpg
Mobile Tracking Protection - Status by Bug - July 29th
Important Links/References
- Work Tracking Spreadsheet
- Meta bug for Tracking Protection work