(New page: == Start of project == * Name each of the following: ** Project sponsor ** Main IT contact ** Main WebDev contact ** Main QA contact ** Main third party contact (if developed externally) *...)
 
mNo edit summary
Line 1: Line 1:
== Start of project ==
== Start of project ==
* Name each of the following:
* Name each of the following:
** Project sponsor
** Project sponsor: Kev Needham
** Main IT contact
** Main IT contact: TBD
** Main WebDev contact
** Main WebDev contact: TBD
** Main QA contact
** Main RelEng contact: Chris Cooper
** Main third party contact (if developed externally)
** Main QA contact: Carsten Book (Tomcat)
** Final application owner/maintainer
** Main third party contact: TBD
** Final application owner/maintainer: John O'Duinn / RelEng
 
* Outline the following:
* Outline the following:
** Overall goal of the project
** Overall goal of the project

Revision as of 14:49, 11 November 2008

Start of project

  • Name each of the following:
    • Project sponsor: Kev Needham
    • Main IT contact: TBD
    • Main WebDev contact: TBD
    • Main RelEng contact: Chris Cooper
    • Main QA contact: Carsten Book (Tomcat)
    • Main third party contact: TBD
    • Final application owner/maintainer: John O'Duinn / RelEng
  • Outline the following:
    • Overall goal of the project
    • Any pre-requisites needed (technology, server capacity, staffing, monitoring, response time, etc)
    • Initial timeline
    • External dependencies
    • Dev environment specs
    • Does this project use any plugins or proprietary technology?

Staging Signoff

In order to get an app into staging, the following should be completed:

  • Code committed to Mozilla source control and tagged
  • Initial architecture review by IT and WebDev
  • Plugin/tech review by Evangelism
  • Site must be password protected
  • Review timeline to go live
  • Review any production requirements so IT can order any new hardware needed

Production Signoff/Launch

  • Final WebDev signoff
  • Final IT signoff
  • Final QA signoff
  • Operations documents filled for support & any training complete
  • Monitors in place