(New page: == Start of project == * Name each of the following: ** Project sponsor ** Main IT contact ** Main WebDev contact ** Main QA contact ** Main third party contact (if developed externally) *...) |
mNo edit summary |
||
| Line 1: | Line 1: | ||
== Start of project == | == Start of project == | ||
* Name each of the following: | * Name each of the following: | ||
** Project sponsor | ** Project sponsor: Kev Needham | ||
** Main IT contact | ** Main IT contact: TBD | ||
** Main WebDev contact | ** Main WebDev contact: TBD | ||
** Main QA contact | ** Main RelEng contact: Chris Cooper | ||
** Main third party contact | ** Main QA contact: Carsten Book (Tomcat) | ||
** Final application owner/maintainer | ** Main third party contact: TBD | ||
** Final application owner/maintainer: John O'Duinn / RelEng | |||
* Outline the following: | * Outline the following: | ||
** Overall goal of the project | ** Overall goal of the project | ||
Revision as of 14:49, 11 November 2008
Start of project
- Name each of the following:
- Project sponsor: Kev Needham
- Main IT contact: TBD
- Main WebDev contact: TBD
- Main RelEng contact: Chris Cooper
- Main QA contact: Carsten Book (Tomcat)
- Main third party contact: TBD
- Final application owner/maintainer: John O'Duinn / RelEng
- Outline the following:
- Overall goal of the project
- Any pre-requisites needed (technology, server capacity, staffing, monitoring, response time, etc)
- Initial timeline
- External dependencies
- Dev environment specs
- Does this project use any plugins or proprietary technology?
Staging Signoff
In order to get an app into staging, the following should be completed:
- Code committed to Mozilla source control and tagged
- Initial architecture review by IT and WebDev
- Plugin/tech review by Evangelism
- Site must be password protected
- Review timeline to go live
- Review any production requirements so IT can order any new hardware needed
Production Signoff/Launch
- Final WebDev signoff
- Final IT signoff
- Final QA signoff
- Operations documents filled for support & any training complete
- Monitors in place