Top level KPI status report April 27, 2016
Overall Project Health
Last week: Green.
This week: Yellow.
Project scope and deliverables
Team is responsible for making sure the engagement ratio is justified and appearing on dashboards. As per Product Management, the ratios that are being targeted (and their date) are:
- FF desktop (Q1) - done
- FxA (Q1) - done
- Mobile (iOS + android) (Q2)
- Best of web - pocket (Q1) done and hello (Q2)
- Test pilot (Q2)
- Activity stream (Q2)
Exec Summary
- Hello in yellow due to tight timeframe and lack of established communication channels
- Test pilot data landing in s3, next steps are .csv and automating job
- Coming changes (Q2) to engagement measures need to be understood and planned for
- Firefox for Android (and Fennec dashboard) are actively being worked on
- Some concern around Rebecca's availability for Q2 and the corresponding project impact.
Kpi's and delivery status
| Description of KPI | Status | Active user definition | justification doc | target date / link to dashboard | next steps | implementation tracking ticket |
|---|---|---|---|---|---|---|
| Firefox desktop ratio | green | done | done | see "ratio" | need to plan steps 2&3 | bugzilla |
| Firefox accounts | green | done | same as FF desktop | 3/8 | wire up to top level dashboard | bugzilla |
| Firefox Mobile - iOS | yellow | TBD | TBD | TBD | Meeting with teams to understand how the ratio is gathered and visualized | bugzilla |
| Firefox Mobile - fennec | Green | TBD | TBD | Q2 | Meeting with teams to understand how the ratio is gathered and visualized | bugzilla |
| green | done | done | done | Done | bugzilla | |
| Hello | yellow | done | done | dashboard landing spot? | bugzilla | |
| Test Pilot | green | in progress | Q2 | test pilot is being tasked with MVP - python notebook and viz. No further PM actions at this time. | bugzilla | |
| Activity Stream | red | yes | same as test pilot | bugzilla |
Accomplished for Last Period
- Test pilot data in s3 bucket (needs to be loaded into presto)
- Once in presto re:dash has a reserved space for dashboard
- Activity stream in Presto
Planned for Upcoming Period
- Mreid working on the .csv aspect as well as making an automated job (need to understand how)
- need to retire is escalate
- Engagement measure and UITelemetry change impact needs to be understood (may need to rev existing dashboards)
- Plan for iOS appearing on dashboard now that core pings has landed
Outstanding requests not yet road mapped into a release
| Description | State | Owner | Plan to Resolve/Mitigation | Target Date |
|---|---|---|---|---|
| Do all items live on a top level dashboard | new | team | Yes, as possible | done |
| pocket and hello do not have unique dashboards for top line KPI's | in process | team | adding to pocket to top line, hello tbd | TBD |
| iOS and Android - use adjust dashboard for KPI's? | new | team/Mobile | ratio does not appear on adjust dashboard, Q2 is goal for bring UT based numbers to populate dashboard | TBD |
| iOS and Android - when does mobile use UT to generate ratio and whats the cut over plan | in process | team/Mobile | timing TBD | TBD |
Important Links/References
- PRD (WIP)
- this includes data format, UI mock ups and delivery schedule
- Bug tree
- weekly meeting notes