Matthew's non-dev tasks for remainder of 2009
- (P0) Provide daily update with status/plans/time requirements
- (P4) Propose policy of limiting total chat time to X minutes in contributors forum
- Blog posts (P2)
- Dec 14: community-powered
- Dec 17: user experience observations
- Dec 21: Bug fixes (single sign-on, performance, win7)
- Dec 28: Proposed policy change for limiting chat time
- Early January: web client status
- (P5) Anchor live chat for 2.5 weeks
- (P5) Improve metrics script to group tags in smarter ways.
- Define tag aliases
- Group tags based on historical correlation
Openfire bugs not required for web client
| Task/priority | Bug # | Estimated hours required | Actual hours spent | Status |
|---|---|---|---|---|
| Openfire support for SUMO single sign-on (P0) | 6 hours | ~7 to-date | Deadline: Tuesday Dec. 15 | |
| Finish replacing RoundRobinDispatcher with FairDispatcher (performance) (P2) | 10 hours | ~6 hours to-date | Deadline: Thursday, Dec. 24
|
Openfire bugs required for web client, highest priority
Goal is to have all existing functionality working and ready to show in next two weeks.
| Task | Bug # | Estimated hours required | Actual hours spent | Status |
|---|---|---|---|---|
| Finalize event model and ajax core functions | 20 hours | Done as of September 30, in subversion testing branch | ||
| Separate live chat code into separate fastpath component for accepting chats | 3 hours | Done
| ||
| Finish writing SimpleLogin widget (P1) | 6 hours | 3 hours to-date | Deadline: Friday, Dec 18 | |
| Write multitab widget (based on jquery UI) and chat tab spawning (P1) | 10 hours | Deadline: Friday, Dec 18 | ||
| Make chatbox widget fully functional | 8 hours | Deadline: Thursday, Dec 24 | ||
| Alert/notify widget based on jquery UI | 4 hours | Deadline: Thursday, Dec 31
| ||
| Fix widget loading, template switching | ~10 hours remaining | Deadline: Thursday, Dec 31 |
Openfire bugs required to replace Spark
| Task | Bug # | Estimated hours required | Actual hours spent | Status |
|---|---|---|---|---|
| Remove obsoleted code, unnecessary debug messages; polish | ~3 hours | |||
| Canned responses | ~8 hours | |||
| Unit tests for event and widget functionality | ? |
Actual time spent
- Friday, Dec 11
- 3 hrs, SUMO login
- Saturday, Dec 12
- Monday, Dec 14
- Tuesday, Dec 15
- Wednesday, Dec 16
- Thursday, Dec 17
- Friday, Dec 18
- Saturday, Dec 19
- Monday, Dec 21 (away)
- Tuesday, Dec 22
- Wednesday, Dec 23
- Thursday, Dec 24 (1/2 day)
- Friday-Sunday (away)