Program Management/Weekly-Status-Reports/2012-05-29

From MozillaWiki
Jump to navigation Jump to search
The printable version is no longer supported and may have rendering errors. Please update your browser bookmarks and please use the default browser print function instead.

Meeting Topics

Dietrich

  • Still underwater :)
  • Private email threads are a huge problem. Making progress on kicking all conversation to public lists though.
  • Moved all meetings from person-status-centric to app/api/feature-status centric based on v1 deliverables. This ensures non-progress and non-ownership is highlighted, less to slip through cracks.
  • Doing weekly summaries of all B2G activity for Monday project-wide meeting and for Basecamp report: https://etherpad.mozilla.org/b2g-status
  • Scheduled weekly triage for Gecko and Gaia
  • Basecamp flags will be available on Thurs
  • Getting a B2G vidyo room so that we can have guests as well as be able to remote mute people
  • While systems are getting better (and quickly), still not all the way there wrt knowing exactly how far behind we are.

Erin

Recent/Current Status

Fennec Native (beta)

  • Convergence and risk-management for beta milestone declare and beta releases beta 1 thru beta 3

Fennec Native (release)

  • Convergence and risk-management for GA
    • Lot's of triage; driving dependencies is first priority after monitoring/helping managing blockers. AMO & engaging with web compat program w/ Lawrence is a focus for this week
    • Phone vs. Tablet plan (working with Alex + driving x-functional conversations)
    • Ongoing status communication
  • Overall: once we hit beta, our cadence as a team has much improved we are sort of in rinse/wash/repeat mode with caveats, of course \o/

Current/Future

K9o

  • Starting to engage as much as possible; helping onboard Karen, our new PM & working on proposal for planning//communicating future releases

Lawrence

  • Published program management Q1 summary.
  • Silent Updates
    • Background updates landed, had to be preffed off, but is no back on and looks like it will stick. This is the last major piece of the silent update program.
  • Kilimanjaro/Basecamp
    • Need to provide more visibility into this project. Will start reporting on Monday project call. (Should coordinate with Dietrich.) Also want to post more information publicly.
  • Snappy
    • Working with perf team to identify work to support k9o.
    • Continuing to make progress with various projects.
    • Ongoing issue of getting attention on this project even though this is priority 4 for the org after mobile, basecamp, and k9o.
  • Mobile Web compat
    • Announced weekly meeting publicly to get more attention on this effort.
    • Planning to give lightening talk about this next week.
    • Working to establish contact with Google (issues on our side).
    • Investigating issues with Microsoft Web properties.
    • Prioritized on Brazilian market to support Basecamp.
  • Telemetry
    • Followed up on enabled-by-default for Aurora and Nightly. Review has been grouped with a larger policy review. Need to understand ramifications on timeline.
    • Making progress on data validation and verification
    • Should complete last privacy requirement, integrating about:telemetry in the platform, shortly (under review).
  • mediawiki-bugzilla
    • There are issues to address. Have time commitment from WebDev team but no time to manage to ensure issues are being resolved.

Martin

Games

  • Worked off site on a special project
  • Banana Bread - Worked with Sheila to get contractor hired

Bugzilla Anthropology

  • Saw progress on nested queries, will be testing them out this week

Mike

  • Started - May 29th, 2012

Sheila

  • Social API
    • Lots of activities going on - SocialAPI component in bugzilla to track items
    • Meeting with Dolske, Gavin, Mike H to review what we have so far
    • Lawrence and I are trying to clean up some of the bugs
    • Not sure how much we will get landed for FF15 - working on some API pieces
  • Kilimanjaro
    • A few things unresolved since PM team was out last week
    • Moved triage sessions - now Mon/Wed
  • Stability work week
    • Brainstorming agenda for work week - https://etherpad.mozilla.org/StabilityWorkWeek
    • Put together daily breakdown by the end of the week - June 1
    • Kairo in town next week - will have him join next week's meeting
    • Many conflicts with channel meetings and other - looking to delegate some crash related activities.
  • Other
    • Rearranging 1:1s
    • Lots of interviews for Apps PM
    • Mike starting this week - will be pulled into a bunch of B2G meetings to help Mike get up to speed