Connected Devices/Projects/Smart Kitchen

< Connected Devices‎ | Projects
Revision as of 16:24, 28 June 2016 by Nyee (talk | contribs) (meeting)
  • Tamara Insert Project Intro

Project overview

  • Tamara Insert Project Overview

Program Status

Milestone Date Status Status Notes
Kick off meeting 3/03/2016 Done Kick off presentation
First Research plan drafted 3/14/2016 Done
Research plan #1 drafted 3/29/2016 Done
Portland working week to analyze the Research findings and set the following goals/milestones 4/08/2016 Done
User Research #2 [from May 25th to 29th] 5/08/2016 Done
London All Hands 6/17/2016 On target
User Research #2 findings Not Started

Status Key

Color Status Key
On Target The project or deliverable is expected to meet its due date.
Challenged The project or deliverable is facing an issue that might cause it to miss its due date, but a “get well” plan has been developed to get it back on track.
At Risk or Late The project or deliverable is blocked or facing an issue that might cause it to miss its due date, and there’s no “get well” plan to get it back on track, or it is already late.
Done The project or deliverable has been completed.
On Hold or Not Started The project or deliverable has either not been started or has been placed on hold.

Archived Completed Deliverables

Milestone Date Status Status Notes
First Research plan drafted 3/14/2016 Done Initial Research Plan is already out of date as it was revisited.
Revised Research plan #1 and Interviews guides 3/29/2016 Done New Research plan created to learn about the needs of the new targeted audiences: Babysitting age (12 to 15 years old) and independent elderly (aging in place). Both have caregivers who question the independence of the 2 audiences. To run this new research plan we'll be using these two Interview Guides together with these Consent & Compensation Forms.
Documentation about our Research findings from the Interviews 4/27/2016 Done Project Haiku: User Study #1
Research plan #2: Interviews guides, Research prototype, Diaries and all the documentation and logistics necessary for the User Study. 5/24/2016 Done Project Haiku - User Study #2. This User Research wants to validate this hypothesis: Creating an ambient method of communicating for 12 to 15 year old girls will create fewer interruptions that distract them from being in the moment at home and at school and improve their personal connections.
Documentation about our Research #2 findings Not Started


Communication

IRC

Join the conversation on irc.mozilla.org, channel #SmartKitchen.

Vidyo


Bi-Weekly Sync Ups

The Smart Kitchen has open bi-weekly sync ups every Tuesday and Thursday at 11:00AM PST in the SmartKitchen Vidyo room. Instructions for joining the video conference (vidyo) meeting room are above. Meeting notes can be found here. -->