QA/Test Automation/2011-06-01
< QA | Test Automation
Jump to navigation
Jump to search
previous meeting | Meetings | next meeting »
Dial in
# 650-903-0800 or 650-215-1282 x92 Conf# 315 (US/INTL) # 1-800-707-2533 (pin 369) Conf# 315 (US) # irc.mozilla.org #mozmill for backchannel
Attendees
Last action items
- Geo: Work with Al and Anthony to get the on-demand update testing running on qa-set (April 27th)
- [DONE] Henrik: Talk to David for a meeting about handling patch reviews with Softvision (include Web Automation)
- It will not happen before Henrik comes back from vacation
- [DONE] Henrik: Create automation scripts for handing new test-run called "remote" (May 19th)
- Anthony: Get in contact with Vlad by end of today to kick of Discovery Pane tests (May 18th)
- Dave: Please reference last meeting notes from endurance meeting if you can't attend
- Al: Collect possible use cases and goals on-demand provisioning
- Al: Create remaining invalid certificates (May 20th)
Goals Overview
Risky Goals
Project Status
On-demand release tests (Geo/Henrik)
- Anthony has discovered issues with the daemon yesterday during release testing. We had to fallback to the old way of running update tests
Endurance Tests (Dave/Anthony)
Others
Mozmill Crowd
- Patch for further launch points (add-on bar, Firefox button) has been landed
- Working on the documentation and the version checker for test environments
Dashboard
- TBD
On Demand Provisioning (Cloud Automation) (Al/Henrik)
- General (Henrik)
- Check-ins since the last meeting
- All broken functional tests have been fixed for branches down to 4.0
- Endurance test for Tab Switching in Panorama is still failing - we really have to ensure to get those kind of failures fixed faster
- Softvision (Anthony)
Shadow web server (Al/Henrik)
Automation Scripts / Infrastructure (Henrik)
Personal Status
For the personal status please check the weekly status updates:
Roundtable
- General
- To ensure a fast progress please work on action items right after the meeting, or at least get the process triggered. Doing that 1 or 2 days before the next meeting will push us back by nearly 2 weeks. (Henrik)
- We have to get better in fixing broken tests. We can't leave broken ones failing for over two weeks! (Henrik)
Meeting Notes
Action items
- Geo: Send pivotaltracker details for API refactoring project to team members