Support/Goals/SUMO-KPI-dashboard
< Support
Jump to navigation
Jump to search
Purpose
Track SUMO KPI and display them in the most effective way
Project plan
- Define KPIs
- Gather requirements for KPIs
- with Cheng, Ibai
- Gather resources to implement KPIs
- with Ricky
- Implement KPIs
- by SUMOdev
How do we know it's done?
- We have a way to request a value for every single KPI
Schedule
Estimated time: 2 month
- Define KPIs: January 1 - January 14
- Gather requirements: January 1 - January 14
- Implementaton: January 14 - February 30
Blocked
NO
Notes
Next step: