MDN/Archives/Dev Milestones

From MozillaWiki
< MDN‎ | Archives
Revision as of 15:24, 23 August 2012 by John Karahalis (talk | contribs)
Jump to navigation Jump to search

Product backlog (running list of all remaining work)

Timeline

  • 8-Jun - general testing period starts
  • 21-30 June - general testing - edit & add content (wiki pages, files, code samples)
  • 7-8 July - bug hunt with Mozilla QA
  • 10-July - deki shut off for updates (browse only) - final content migration, link to kuma "beta" for browsing
  • 10-15 July - writing/editing on kuma, continue testing, verify bug fixes
  • 16-July - cutover

Development Sprints

The Kuma development team is using the Scrum method of agile software development. Our sprints are two weeks and code is pushed weekly. See below for details on what bugs are addressed in each sprint.

Sprint ending September 5, 2012

Sprint ending August 15, 2012

Sprint ending August 8, 2012

Sprint ending August 1, 2012

Sprint ending July 17, 2012

Sprint ending July 15, 2012

Sprint ending 03-July-2012

Sprint ending 19-June-2012

Sprint ending 19-June-2012

Sprint ending 05-June-2012

Sprint ending 22-May-2012

Sprint ending 08-May-2012

Sprint ending 24-April-2012

Sprint ending 10-April-2012