BMO/Meetings/2016-01-05
From MozillaWiki
- Q4 goal status:
- [dylan] wrapping up his this week
- [dkl] upstream merge has green test run; needs wider testing and a deployment plan. Fubar setting up the test cluster.
- Testing plan: use UAT from Nubis move. Advertise for testers on tools.bmo.
- Deployment plan: will require downtime; should plan for a TCW. Needs CAB approval.
- Q1 goals
- [dkl] bug 232193 Database timezone conversion to UTC: code & testing. Actual conversion in Q2.
- [dylan] bug 1184823 QuickSearch via Elastic Search. Goal is for dev only. Stretch for production.
- [glob] bug 1150541 Soft goal: bug modal.
- [glob] fxa
- Aim to get this in before end of Q2.
- [glob] nubis
- Deferred discussion until fubar is around.
- [glob] logging and alerting - papertrailapp.com?
- Might want to do this but would need security's input first.