Firefox/Activity Stream/Status/04-Apr-2017
From MozillaWiki
< Firefox | Activity Stream | Status
Firefox Activity Stream Program - Cross-Platform Status Report - Apr-04-2017
Overall Project Health
On track, issues well managed Some risks, unknowns without clear mitigations Blocked on deliverables, needs decision, escalation required
Platform/Area | Version | Health | Notes |
---|---|---|---|
Desktop | FF57 | MVP feature development progressing well. 'Wapusk' sprint was kicked off Apr 3rd, ending Apr 16th. Revised Graduation work broken down, and new schedule generated, targeting FF57. | |
Android | FF?? | Sprint 1.19 (ending Apr 16) has been kicked off. Team capacity still impacted by ~66% as resources temporarily assigned to another higher priority initiative (Focus Android). Schedule will be re-baselined once all resources are back on board, which should be late April. | |
iOS | V8.0 | Sprint 1.19 (ending Apr 16) has been kicked off; V8.0 now in stabilization. MVP feature development on track for V8.0, and the outstanding MVP bug list tracking 8.0 is getting very short. |
Exec Summary/Hot Topics
Desktop
- Current Sprint 'Wapusk
- Graduation plans have been finalized and work breakdown completed. A new schedule baseline has been generated to accout for the additional work, and is now tracking to land in FF57.
Android
- Current Sprint 1.19
- Continuing on with remaining MVP feature development. MVP Backlog can be found here.
- Schedule will need to re-baselined once all resources are back in place. 2/3 of team has been reassigned temporarily to another high-priority initiative (Focus for Android). Currently anticipate having the team back at full strength in late April, at which point a new schedule will be communicated.
iOS
- Current Sprint 1.19
- Continuing on with remaining MVP feature development. MVP Backlog can be found here.
- MVP Development on track for V8.0. The MVP backlog of tracking bugs is getting very small!
Risks & Issues
Description of Risk/Issue | Affected Platform(s) | State | Owner | Version | Plan to Resolve/Mitigation | Target Date |
---|---|---|---|---|---|---|
Android AS resource availability | Android | Open | Eng | 2/3 Android resources temporarily reassigned. | Apr 30 | |
Development Status
On track, issues well managed Some risks, unknowns without clear mitigations Blocked on deliverables, needs decision, escalation required
For more details please visit:
- Desktop Activity Stream Trello Board
- Android Activity Stream Trello Board
- iOS Activity Stream Trello Board
Please see the following for detailed development state (bug level):
- Desktop MVP Project on GitHub
- Mobile Sprint Planning - iOS & Android - Shows both current sprint, and MVP backlog remaining
- Mobile Performance - work completed to date for both iOS & Android