Status for August 5, 2015
Overall Project Health - GREEN
- We are making progress against all the Q3 goals in a timely manner.
Timeline & Scope
- Q3 Goals:
- Client support for system add-ons install and update (Tracking: 1183866)
- Implement lightweight build, test, and release pipeline for go-faster (Tracking: 1184524)
- Ship v1 of Firefox Experiments / Idea Town (Tracking: 1184527)
- Security policy updates through new update service ("Balrog 2.0") (Tracking: 1184528)
- Q4 Goals:
- Implement Hello UI as an add-on, and ship it via go-faster
- Ship Universal Search as a Firefox Experiment
Exec Summary
- Q3/4 goals in place and currently on track.
- Team is now in place with resources for all major project areas
- Project infrastructure (wiki, mailing list, tracking bugs) established
- Product Requirements Document in progress, to be done this week
Risks/Issues
- We were concerned about having resources to build the test implementation of Hello in Q3 but we have now scoped it appropriately (test implementation only) and the risk is mitigated.
Accomplished for Week
- Project Infrastructure (Laura/Larissa)
- Project requirments doc coming soon.
- New weekly meeting for Updates sub-team in place.
- Fast Fennec
- Met with fennec team to establish collaboration and shared work. L10N requirements being scoped.
- Client integration (Mossop/rhelmer)
- https://wiki.mozilla.org/Firefox/Go_Faster/Client_Requirements
- https://bugzil.la/1183866: [Go Faster] Q3 tracking - Client support for system add-ons install and update
- Build pipeline (mrrrgn)
- https://wiki.mozilla.org/Firefox/Go_Faster/Release_Pipeline
- https://bugzil.la/1184524: [Go Faster] Q3 Goal Tracking - Implement lightweight build, test, and release pipeline for go-faster
- IdeaTown (nchapman)
- "Master Plan" https://docs.google.com/document/d/1bew13QgnGriiMEEZMnI7XP6P2ieq6KiE0t4tDzrqcxQ/
- https://bugzil.la/1184527: [Go Faster] Q3 Goal Tracking - Ship v1 of Firefox Experiments / Idea Town
- This week the lightweight front end will go live to gauge interest in the community and among engaged users
- Updates (tarek)
- new weekly meeting in place starting next Wednesday August 13
- architecture doc: https://docs.google.com/document/d/1SI15ORlfsVcADerO9kSW31S5IUCYAsYlXSFS2Lbvo_s/edit
- https://bugzil.la/1184528: [Go Faster] Q3 Goal Tracking -Security policy updates through new update service ("Balrog 2.0")
Planned for Upcoming Week
- Project Infrastructure (Laura/Larissa)
- determine platform support
- set up wiki-integrated bug queries
- Product Requirements Document
- Client integration (Mossop/rhelmer)
- see: https://wiki.mozilla.org/Firefox/Go_Faster/Client_Requirements
- requirements doc nearly final, coding will begin this week
- Build pipeline (mrrrgn)
- making progress now that the hello test add-on is a real plan
- get relevant bugs attached to tracking bug 1184524
- IdeaTown (nchapman)
- first iteration of the Idea Town splash page + social media to gauge interest
- Iterating on "master plan" to establish minimum viable product separate from experiments themselves
- get relevant bugs attached to tracking bug 1184527
- Updates (tarek)
- get relevant bugs attached to tracking bug 1184528
- Intent to build out Balrog 2.0 for go-faster updates