Discussion Items
- QAE 2009 Story (tchung)
- Feedback?
- QAE 2009 Goals (tchung)
- Using QA story, start with Team Goals
- Then break into quarterly
- Refer back to Q3 2008 goals for thoughts
- QMO2 Update (jay)
- QA workweek
- For Bocce ball/Dinner team event, Vote these options:
- 5:30-7pm dinner / 7-8pm Bocce ball court
- 7-8:30pm dinner / 8:30-9:30pm Bocce ball court
- 7-8pm Bocce Ball Court / 8-9:30pm Dinner
- Or just rent a court for 1 1/2 hours (starting at 7pm) and order appetizers, No dinner
- Any other items to add?
- For Bocce ball/Dinner team event, Vote these options:
Project Updates
- Firefox 2.0.0.19/3.0.5 (abillings)
- ETA to beta 12/9
- ETA to live 12/16
- MU 2.0.018 -> 3.0.4 (abillings)
- ETA to live 12/4
- Firefox 3.1 (tchung)
- Beta 2 influx
- ETA to ship Friday, 12/5
- Webdev update (stephend)
- AMO 4.0.4
- Freeze Monday, Dec. 8th
- Pushing Thursday, Dec. 11th
- SUMO
- 0.7.3 shipped last night
- 0.8
- Freeze Tuesday, Dec. 9th
- Push Tuesday, Dec. 16th
- Community Store
- Shipping tomorrow, Dec. 4th
- AMO 4.0.4
- Mobile update (joelm)
- Mobile work week next week
- Alpha 2 testing next week, release on Dec 16th
- I need to finalize test plan
- Litmus smoketests and BFT's are done for Alpha2
- Automation is almost all running on device, investigating failures
- Accessibility update (MarcoZ)
- Other items?